Permit: TC-MDP-0624-00718
Permit Details
Apply Date:
06/28/2024
Applicant:
Dana Petty
Description:
SFR 230.2380 T21-M0028
Permit Reviews
Permit Number - TC-MDP-0624-00718
Permit Status: Issued
Permit Description: SFR 230.2380 T21-M0028
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/28/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 07/01/2024 | APPROVED |
01/06/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/07/2025 | APPROVED |
Conditions
Permit Number - TC-MDP-0624-00718
Permit Status: Issued
Permit Description: SFR 230.2380 T21-M0028
Date | Description | Comments |
---|---|---|
06/28/2024 | Post-Installed Anchor Inspection Report is required. | |
06/28/2024 | Post-Tension Inspection Report is required. | |
06/06/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
06/06/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
06/28/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-MDP-0624-00718
Permite Description: SFR 230.2380 T21-M0028
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/19/2024 | COT - RSBU - Interior Shear Bracing | N/A | Not Applicable | 11-19-24, not ready. Will inspect shear walls when drywall is installed. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-MDP-0624-00718
Permit Description: SFR 230.2380 T21-M0028
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/25/2024 | COT - RSPL - Yard Water Line | Passed | 10-25-24, approved. Okay to backfill. | |
10/25/2024 | COT - RSPL - Sewer | Passed | 10-25-24, approved. Okay to backfill. | |
10/25/2024 | COT - RSPL - Rough Soil | Passed | 10-25-24, approved. Okay to backfill. | |
11/04/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 11-4-24, excavation/setbacks per approved plans. Okay to pour concrete. | |
11/04/2024 | COT - RSBU - Preslab | Passed | 11-4-24, preslab verified per approved plans. Okay to pour concrete. | |
11/04/2024 | COT - RSEL - Electrical Underground | Passed | 11-4-24, electrical underground per approved plans. Okay to pour concrete. | |
11/04/2024 | COT - RSEL - Grounding/Bonding | Passed | 11-4-24, grounding/bonding per approved plans. Okay to pour concrete. | |
11/19/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | 11-19-24, listed items from previous inspection have been corrected. | |
11/19/2024 | COT - RSBU - Roof Nailing | Passed | 11-19-24, listed items from previous inspection have been corrected. | |
12/09/2024 | BULD - Electrical Clearance | Passed | 12-9-24, panel approved to be energized. ECO clearance issued to TEP. | |
12/09/2024 | COT - RSPL - Gas Pressure Test | Passed | 12-9-24, approved | |
12/11/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 12/11/24 corrections made | |
12/23/2024 | COT - RSBU - Interior Shear Bracing | Passed | 12/23/24 shear walls per plan, ok to proceed | |
12/23/2024 | RSBU - Building Progress | Passed |