Permit: TC-MDP-0624-00693
Permit Details
Status:
Complete
Type:
Model Building Permit
Address:
6785 E PASEO DON OCTAVIO
Address NEW:
6785 E PASEO DON OCTAVIO
Apply Date:
05/30/2024
Applicant:
Dana Petty
Description:
SFR 130.1600 T21-M0030
Permit Reviews
Permit Number - TC-MDP-0624-00693
Permit Status: Complete
Permit Description: SFR 130.1600 T21-M0030
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/28/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 07/01/2024 | APPROVED |
| 01/28/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/28/2025 | APPROVED |
Conditions
Permit Number - TC-MDP-0624-00693
Permit Status: Complete
Permit Description: SFR 130.1600 T21-M0030
| Date | Description | Comments |
|---|---|---|
| 07/01/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 07/01/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 07/01/2024 | Post-Tension Inspection Report is required. | |
| 06/03/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 06/03/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
| 07/01/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0624-00693
Permite Description: SFR 130.1600 T21-M0030
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/19/2024 | BULD - Electrical Clearance | N/A | Partial Pass | 12/19/24 TEP clearance code: ECO |
| 12/19/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | 12/19/24Drain and vent are not under test. Penetrations in vapor barriers, fire blocking needed, bedroom off of foyer has extra electrical register, ceiling fans cannot have drywall screws. INSPECTION STOPPED. |
| 12/19/2024 | COT - RSPL - Gas Pressure Test | N/A | Re-inspection required | 12/19/24 gauge is at 6 PSI re inspection required |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0624-00693
Permit Description: SFR 130.1600 T21-M0030
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/14/2024 | COT - RSPL - Yard Water Line | Passed | 11-14-24, main water line, sewer connection,setbacks, underground plumbing approved. Okay to backfill-provide shading. | |
| 11/14/2024 | COT - RSPL - Sewer | Passed | 11-14-24, main water line, sewer connection,setbacks, underground plumbing approved. Okay to backfill-provide shading. | |
| 11/14/2024 | COT - RSPL - Rough Soil | Passed | 11-14-24, main water line, sewer connection,setbacks, underground plumbing approved. Okay to backfill-provide shading. | |
| 11/20/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 11-20-24, excavation/rebar/zoning,grounding/bonding, electrical underground approved. Okay to pour concrete. | |
| 11/20/2024 | COT - RSBU - Preslab | Passed | 11-20-24, grounding/bonding, electrical underground, preslab verified as per approved plans. Okay to pour concrete. | |
| 11/20/2024 | COT - RSEL - Electrical Underground | Passed | 11-20-24, grounding/bonding, electrical underground approved. Okay to pour concrete. | |
| 11/20/2024 | COT - RSEL - Grounding/Bonding | Passed | 11-20-24, grounding/bonding approved. | |
| 12/06/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 12-6-24, exterior clips/sheathing and roof nailing approved. | |
| 12/06/2024 | COT - RSBU - Roof Nailing | Passed | 12-6-24, exterior clips/sheathing and roof nailing approved. | |
| 12/23/2024 | BULD - Electrical Clearance | Passed | TEP clearance code: ECO | |
| 12/23/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 12/23/24 corrections made | |
| 12/23/2024 | COT - RSPL - Gas Pressure Test | Passed | 12/23/24 corrections made | |
| 01/14/2025 | COT - RSBU - Interior Shear Bracing | Passed | Passed 1/14/25 ok to tape | |
| 02/20/2025 | COT - BULD - SWG Clearance | Passed | 2/19/25 approval for SWG clearance | |
| 03/06/2025 | COT - RSEL - Electrical Final | Passed | 6 Mar 25 Pass |
|
| 03/06/2025 | RSBU - Building Progress | Passed | ||
| 03/06/2025 | RSBU - Building Final | Passed | ||
| 03/06/2025 | COT - RSPL - Plumbing Final | Passed | 6 Mar 25 Pass |
|
| 03/06/2025 | COT - RSME - Mechanical Final | Passed | 6 Mar 25 Pass |
|
| 03/06/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 03/18/2025 | ENGR Engineering Final | Passed | CO Ready |