Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
07/10/2023
Applicant:
Eric Touhey
Description:
ADU Model Plan Lumen

Permit Reviews

Permit Number - TC-MDP-0623-01218
Permit Status: Complete
Permit Description: ADU Model Plan Lumen
Start Date Submittal Complete Date Status  
07/11/2023 SITE FROM MODEL PERMIT - PRODUCTION v.1 07/13/2023 APPROVED Review Details
08/24/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/01/2023 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0623-01218
Permit Status: Complete
Permit Description: ADU Model Plan Lumen
Date Description Comments
07/13/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit.
07/12/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
09/08/2023 Contractor Roc# only allows for projects of $50,000 or less. Valuation of project listed as $128,236.98

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0623-01218
Permite Description: ADU Model Plan Lumen
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
10/19/2023 COT - RSPL - Rough Soil N/A Re-inspection required 1-Piping is covered. 2-Washer is located in wrong area. 3-Several pipe sizes are incorrect.
07/09/2024 COT - BULD - SWG Clearance N/A Not Applicable
07/09/2024 COT - RSPL - Gas Pressure Test N/A Not Applicable No gas service at the site.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0623-01218
Permit Description: ADU Model Plan Lumen
Total Completed Inspections - 19
Date Description Inspector Results Comments
10/20/2023 COT - RSPL - Rough Soil Passed 10/20/23: Underground plumbing pipes have been exposed, washer drain line has been relocated, all incorrect pipe sizes have been replaced with the correct pipe size. Okay to shade pipes and backfill trenches.
10/20/2023 COT - RSPL - Yard Water Line Passed Main water line is connected to house main water supply line. Okay to shade water line and backfill trench.
11/01/2023 COT - RSBU - Preslab Passed 11-1-23: Pre-slab is properly compacted, rebar reinforcement is in place, sewer pipes running through foundation are properly wrapped with foam insulation. Okay to pour concrete for footings and slab.
11/13/2023 COT - RSEL - Electrical Underground Passed 11/13/23: electrical underground for ADU and Studio per plan ok to backfill.
03/04/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
03/04/2024 COT - RSBU - Interior Shear Bracing Passed
03/04/2024 COT - RSBU - Roof Nailing Passed
03/06/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Plumbing, electrical, and mechanical rough-in are complete. Okay to proceed with drywall, tape, and texture installation.
04/25/2024 BULD - Electrical Clearance Passed clearance for TEP INCR. At ADU NEW 400 AMP SERVICE PANEL. 4/25/2024
07/03/2024 RSBU - Building Final Passed
07/09/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
07/09/2024 COT - RSEL - Electrical Final Passed
07/09/2024 COT - RSEL - Grounding/Bonding Passed
07/09/2024 COT - RSEL - Outdoor Lighting Passed
07/09/2024 COT - RSME - Mechanical Final Passed
07/09/2024 COT - RSPL - Plumbing Final Passed
07/09/2024 COT - RSPL - Sewer Passed
07/09/2024 RSBU - Building Progress Passed
07/24/2024 ENGR Engineering Final Passed All items installed per plan

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
SIGNED OBA_V1.PDF DOCUMENTS VIEW
REV1_DEFERRED SUBMITTAL_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-1_PLAN SET_V1.PDF DOCUMENTS VIEW