Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
07/31/2023
Applicant:
Celina Rodriguez
Description:
SFR BT1842-135 T22-M0035

Permit Reviews

Permit Number - TC-MDP-0623-01208
Permit Status: Inspections complete
Permit Description: SFR BT1842-135 T22-M0035
Start Date Submittal Complete Date Status  
08/02/2023 SITE FROM MODEL PERMIT - PRODUCTION v.1 08/03/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0623-01208
Permit Status: Inspections complete
Permit Description: SFR BT1842-135 T22-M0035
Total Outstanding Activity Conditions - 3
Date Name
08/02/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
08/02/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
08/03/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-0623-01208
Permit Status: Inspections complete
Permit Description: SFR BT1842-135 T22-M0035
Date Description Comments
05/24/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
08/02/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0623-01208
Permit Description: SFR BT1842-135 T22-M0035
Total Completed Inspections - 21
Date Description Inspector Results Comments
08/18/2023 COT - RSPL - Yard Water Line Passed
08/18/2023 COT - RSPL - Sewer Passed
08/18/2023 COT - RSPL - Rough Soil Passed
09/01/2023 COT - RSBU - Excavation/Rebar/Zoning Passed
09/01/2023 COT - RSBU - Preslab Passed
09/01/2023 COT - RSEL - Electrical Underground Passed
09/01/2023 COT - RSEL - Grounding/Bonding Passed
09/18/2023 COT - RSBU - Roof Nailing Passed
10/19/2023 COT - RSPL - Gas Pressure Test Passed
10/19/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
10/19/2023 COT - RSBU - Exterior Clips/Sheathing Passed
11/01/2023 COT - RSBU - Interior Shear Bracing Passed
11/17/2023 BULD - Electrical Clearance Passed 11/17/23: TEP ECO
01/18/2024 COT - BULD - SWG Clearance Passed SWG for meter only
01/22/2024 COT - RSEL - Electrical Final Passed
01/22/2024 COT - RSEL - Outdoor Lighting Passed
01/22/2024 COT - RSME - Mechanical Final Passed
01/22/2024 RSBU - Building Progress Passed
01/22/2024 ENGR Engineering Final Passed
01/23/2024 COT - RSPL - Plumbing Final Passed
01/23/2024 RSBU - Building Final Passed 1/23/24: all corrections made

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
BELLA TIERRA II 61 SIC-2023-07-31_V1.PDF DOCUMENTS VIEW
BELLA TIERRA PHASE 2 - LOT 61 START_V1.PDF DOCUMENTS VIEW
P21WP00207 FINAL ACCEPTANCE BTII_V1.PDF DOCUMENTS VIEW