Permit: TC-MDP-0623-01196
Permit Details
Apply Date:
08/08/2023
Applicant:
David Martin
Description:
SFR K35G T21-M0033
Permit Reviews
Permit Number - TC-MDP-0623-01196
Permit Status: Complete
Permit Description: SFR K35G T21-M0033
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/15/2024 | APPROVED |
08/08/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 08/09/2023 | APPROVED |
Conditions
Permit Number - TC-MDP-0623-01196
Permit Status: Complete
Permit Description: SFR K35G T21-M0033
Date | Description | Comments |
---|---|---|
08/08/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
08/08/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
03/15/2024 | Post-Tension Inspection Report is required. | |
06/15/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
06/27/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
06/15/2023 | Sewer condition must be accepted and released by Pima County | |
08/08/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0623-01196
Permit Description: SFR K35G T21-M0033
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/10/2023 | COT - RSPL - Rough Soil | Passed | Okay to back fill. Shading is required. 10/10/2023 | |
10/10/2023 | COT - RSPL - Sewer | Passed | Okay to back fill. Shading is required. 10/10/2023 | |
10/10/2023 | COT - RSPL - Backwater Valve | Passed | Okay to back fill. Shading is required. 10/10/2023 | |
10/10/2023 | COT - RSPL - Yard Water Line | Passed | Okay to back fill. Shading is required. 10/10/2023 | |
10/16/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
10/16/2023 | COT - RSBU - Preslab | Passed | ||
10/16/2023 | COT - RSEL - Electrical Underground | Passed | ||
10/16/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
11/01/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
11/01/2023 | COT - RSBU - Roof Nailing | Passed | ||
11/29/2023 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 11/29/2023 | |
11/29/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
11/30/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
12/14/2023 | COT - RSBU - Interior Shear Bracing | Passed | Ok to tape and texture throughout | |
02/02/2024 | COT - BULD - SWG Clearance | Passed | Clearance for Southwest Gas. 2/2/2024 | |
03/04/2024 | COT - RSEL - Electrical Final | Passed | ||
03/04/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
03/04/2024 | COT - RSME - Mechanical Final | Passed | ||
03/04/2024 | COT - RSPL - Plumbing Final | Passed | ||
03/04/2024 | RSBU - Building Final | Passed | ||
03/04/2024 | RSBU - Building Progress | Passed | ||
03/08/2024 | ENGR Engineering Final | Passed |