Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
07/26/2023
Applicant:
Andrea Flood
Description:
SFR F40G22 T22-M0025 Revision-Truss Calcs

Permit Reviews

Permit Number - TC-MDP-0623-01187
Permit Status: Complete
Permit Description: SFR F40G22 T22-M0025 Revision-Truss Calcs
Start Date Submittal Complete Date Status  
10/10/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/10/2023 APPROVED Review Details
07/27/2023 SITE FROM MODEL PERMIT - PRODUCTION v.1 07/28/2023 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0623-01187
Permit Status: Complete
Permit Description: SFR F40G22 T22-M0025 Revision-Truss Calcs
Date Description Comments
07/27/2023 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
07/27/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
07/27/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
10/10/2023 Post-Tension Inspection Report is required.
06/27/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
07/20/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
07/20/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
07/27/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
07/28/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0623-01187
Permit Description: SFR F40G22 T22-M0025 Revision-Truss Calcs
Total Completed Inspections - 21
Date Description Inspector Results Comments
08/09/2023 COT - RSPL - Rough Soil Passed
08/09/2023 COT - RSPL - Sewer Passed
08/16/2023 COT - RSBU - Excavation/Rebar/Zoning Passed
08/16/2023 COT - RSBU - Preslab Passed
08/16/2023 COT - RSEL - Electrical Underground Passed
08/16/2023 COT - RSEL - Grounding/Bonding Passed
08/30/2023 COT - RSBU - Roof Nailing Passed
09/08/2023 COT - RSBU - Exterior Clips/Sheathing Passed
10/05/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
10/05/2023 COT - RSPL - Gas Pressure Test Passed
10/05/2023 COT - RSPL - Yard Water Line Passed
10/06/2023 BULD - Electrical Clearance Passed 10/5/23 Missing breaker and blank plate on dead front
10/6/23: ECO TEP Clearance
10/30/2023 COT - RSBU - Interior Shear Bracing Passed
12/08/2023 COT - BULD - SWG Clearance Passed SWG clearance issued.
01/10/2024 COT - RSEL - Electrical Final Passed
01/10/2024 COT - RSEL - Outdoor Lighting Passed
01/10/2024 COT - RSME - Mechanical Final Passed
01/10/2024 COT - RSPL - Plumbing Final Passed
01/10/2024 RSBU - Building Final Passed
01/10/2024 RSBU - Building Progress Passed
01/10/2024 ENGR Engineering Final Passed

Documents

File Name Document Type  
152455 SAGUARO TRAILS PT REPORT LOT 4387-2023-10-09_V1.PDF DOCUMENTS VIEW
SPAPP-P22WP00131 FINAL ACCEPTANCE-2023-10-09_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_APPLICATION_V1.PDF DOCUMENTS VIEW
1_SITEPLAN_REVISION_NARRATIVE_V1.PDF DOCUMENTS VIEW
1_SITEPLAN_V1.PDF DOCUMENTS VIEW
1_SPECIAL INSPECTION CERT-2023-07-26_V1.PDF DOCUMENTS VIEW
CONS-1_SITEPLAN_387_V1.PDF DOCUMENTS VIEW