Permit: TC-MDP-0623-01147
Permit Details
Apply Date:
08/10/2023
Applicant:
Daria Hopkins
Description:
SFR MERI213021 T21-M0065
Permit Reviews
Permit Number - TC-MDP-0623-01147
Permit Status: Complete
Permit Description: SFR MERI213021 T21-M0065
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/11/2023 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 08/15/2023 | APPROVED |
10/21/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/22/2024 | APPROVED |
10/02/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/02/2023 | APPROVED |
Conditions
Permit Number - TC-MDP-0623-01147
Permit Status: Complete
Permit Description: SFR MERI213021 T21-M0065
Date | Description | Comments |
---|---|---|
10/02/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
08/11/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
08/11/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
08/14/2023 | Post-Tension Inspection Report is required. | |
06/09/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
08/11/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
08/14/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0623-01147
Permite Description: SFR MERI213021 T21-M0065
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/22/2024 | BULD - Electrical Clearance | N/A | Not Ready | 3/22/24: not ready |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0623-01147
Permit Description: SFR MERI213021 T21-M0065
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/31/2023 | COT - RSPL - Rough Soil | Passed | ||
10/31/2023 | COT - RSPL - Sewer | Passed | ||
11/08/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Rebar reinforcement is in place per plans, post tension cabling is installed and properly supported off of ground, Ufer ground is in place and the proper length, underground electrical for kitchen island is properly installed, plumbing pipes are properly wrapped with styrofoam sheeting, and subsoil is properly compacted. Okay to pour concrete for slab on grade. | |
11/08/2023 | COT - RSEL - Electrical Underground | Passed | Rebar reinforcement is in place per plans, post tension cabling is installed and properly supported off of ground, Ufer ground is in place and the proper length, underground electrical for kitchen island is properly installed, plumbing pipes are properly wrapped with styrofoam sheeting, and subsoil is properly compacted. Okay to pour concrete for slab on grade. | |
11/08/2023 | COT - RSEL - Grounding/Bonding | Passed | Rebar reinforcement is in place per plans, post tension cabling is installed and properly supported off of ground, Ufer ground is in place and the proper length, underground electrical for kitchen island is properly installed, plumbing pipes are properly wrapped with styrofoam sheeting, and subsoil is properly compacted. Okay to pour concrete for slab on grade. | |
11/08/2023 | COT - RSBU - Preslab | Passed | Rebar reinforcement is in place per plans, post tension cabling is installed and properly supported off of ground, Ufer ground is in place and the proper length, underground electrical for kitchen island is properly installed, plumbing pipes are properly wrapped with styrofoam sheeting, and subsoil is properly compacted. Okay to pour concrete for slab on grade. | |
12/06/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | All exterior shear walls are properly secured to concrete floor with bolts or Simpson hold downs. All rafters and floor joists have H2.5 clips attached to rafters/trusses and wall top plate. Okay to proceed with dry-in of walls and roof. | |
12/06/2023 | COT - RSBU - Roof Nailing | Passed | All exterior shear walls are properly secured to concrete floor with bolts or Simpson hold downs. All rafters and floor joists have H2.5 clips attached to rafters/trusses and wall top plate. Okay to proceed with dry-in of walls and roof. | |
12/08/2023 | COT - RSPL - Yard Water Line | Passed | ||
01/25/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
01/29/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
02/12/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
04/02/2024 | BULD - Electrical Clearance | Passed | 3/22/24: not ready 4/2/24: ECO |
|
04/12/2024 | COT - BULD - SWG Clearance | Passed | ||
05/16/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
05/16/2024 | ENGR Engineering Final | Passed | ||
05/16/2024 | RSBU - Building Progress | Passed | ||
05/22/2024 | COT - RSEL - Electrical Final | Passed | ||
05/22/2024 | COT - RSME - Mechanical Final | Passed | ||
05/22/2024 | COT - RSPL - Plumbing Final | Passed | ||
05/22/2024 | RSBU - Building Final | Passed |