Permit: TC-MDP-0524-00666
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
10191 S ARNOLD RANCH CT
Address NEW:
10191 S ARNOLD RANCH CT
Apply Date:
09/25/2024
Applicant:
Description:
SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2 Structural calcs and Post grade, Revision V3 7/21/2023 - Structural revision.
Permit Reviews
Permit Number - TC-MDP-0524-00666
Permit Status: Inspections complete
Permit Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2
Structural calcs and Post grade, Revision V3 7/21/2023 - Structural revision.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/26/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 10/02/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0524-00666
Permit Status: Inspections complete
Permit Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2
Structural calcs and Post grade, Revision V3 7/21/2023 - Structural revision.
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 05/28/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
| 09/27/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 09/27/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 09/27/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 09/27/2024 | Post-Tension Inspection Report is required. |
| 09/27/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0524-00666
Permit Status: Inspections complete
Permit Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2
Structural calcs and Post grade, Revision V3 7/21/2023 - Structural revision.
| Date | Description | Comments |
|---|---|---|
| 05/28/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 09/27/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00666
Permite Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2
Structural calcs and Post grade, Revision V3 7/21/2023 - Structural revision.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/06/2024 | COT - RSEL - Grounding/Bonding | N/A | Partial Pass | Ufer ground is in place. PARTIAL PASS. |
| 01/24/2025 | COT - BULD - SWG Clearance | N/A | Canceled | Not Ready--Drywall not installed and gas valves not installed. Cancelled by Carlos. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00666
Permit Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2
Structural calcs and Post grade, Revision V3 7/21/2023 - Structural revision.
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/29/2024 | COT - RSPL - Yard Water Line | Passed | 10-29-24, main water line inspection approved. Okay to backfill. | |
| 10/29/2024 | COT - RSPL - Sewer | Passed | 10-29-24, sewer connection approved. Okay to backfill. | |
| 10/29/2024 | COT - RSPL - Rough Soil | Passed | 10-29-24, underground plumbing approved. Okay to backfill. | |
| 11/06/2024 | COT - RSBU - Preslab | Passed | Okay to pour concrete. Rebar placement matches plan requirements. | |
| 11/06/2024 | COT - RSEL - Electrical Underground | Passed | Okay to pour concrete. Rebar placement matches plan requirements. | |
| 11/06/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Okay to pour concrete. Rebar placement matches plan requirements. | |
| 12/24/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 12/24/24 corrections made, no additional items found | |
| 12/24/2024 | COT - RSBU - Roof Nailing | Passed | 12/24/24 corrections made, no additional items found | |
| 01/22/2025 | BULD - Electrical Clearance | Passed | 1/22/25 pass approval for TEP ECO | |
| 01/23/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 1/23/25. Missing blocking at register in hallway, leak in copper from main water lines. 1/23/25 corrections were made and pictures sent me me. |
|
| 01/23/2025 | COT - RSPL - Gas Pressure Test | Passed | 1/23/25 pass | |
| 01/28/2025 | COT - RSEL - Grounding/Bonding | Passed | 1/28/25 pass | |
| 02/07/2025 | COT - RSBU - Interior Shear Bracing | Passed | Passed interior shear wall inspection 2/7/24 ok to tape | |
| 03/19/2025 | COT - BULD - SWG Clearance | Passed | 3/19/25 CLEARANCE SWG | |
| 04/02/2025 | COT - RSEL - Electrical Final | Passed | Passed final 4/2/25 CLEARANCE ECO | |
| 04/02/2025 | COT - RSEL - Outdoor Lighting | Passed | Passed final 4/2/25 | |
| 04/02/2025 | COT - RSME - Mechanical Final | Passed | Passed final 4/2/25 | |
| 04/02/2025 | COT - RSPL - Plumbing Final | Passed | Passed final 4/2/25 | |
| 04/02/2025 | ENGR Engineering Final | Passed | Site is good. CofO ready. | |
| 04/02/2025 | RSBU - Building Final | Passed | Passed final 4/2/25 | |
| 04/02/2025 | RSBU - Building Progress | Passed | Passed final 4/2/25 |