Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/21/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 06/21/2024 | REQUIRES RESUBMIT |
06/21/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.2 | 06/25/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0524-00660
Permit Status: Inspections
Permit Description: Arches Model Plan
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
05/28/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
06/25/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
06/25/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
06/25/2024 | Post-Tension Inspection Report is required. |
06/25/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0524-00660
Permit Status: Inspections
Permit Description: Arches Model Plan
Date | Description | Comments |
---|---|---|
06/25/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
05/28/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
06/25/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0524-00660
Permite Description: Arches Model Plan
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/12/2024 | COT - RSPL - Yard Water Line | N/A | Re-inspection required | 12-12-24, gauge at 0 psi. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0524-00660
Permit Description: Arches Model Plan
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/03/2024 | COT - RSPL - Rough Soil | Passed | 12-3-24, underground plumbing verified as per approved plans. | |
12/03/2024 | COT - RSPL - Sewer | Passed | 12-3-24, sewer connection verified as per approved plans. | |
12/12/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 12-12-24, grounding/bonding,electrical underground,excavation/rebar and setbacks verified per approved plans. Okay to pour concrete. | |
12/12/2024 | COT - RSBU - Preslab | Passed | 12-12-24, preslab, grounding/bonding,electrical underground,excavation/rebar and setbacks verified per approved plans. Okay to pour concrete. | |
12/12/2024 | COT - RSEL - Electrical Underground | Passed | 12-12-24, preslab, grounding/bonding,electrical underground,excavation/rebar and setbacks verified per approved plans. Okay to pour concrete. | |
12/12/2024 | COT - RSEL - Grounding/Bonding | Passed | 12-12-24, grounding/bonding,electrical underground,excavation/rebar and setbacks verified per approved plans. Okay to pour concrete. | |
12/24/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | No | |
12/24/2024 | COT - RSBU - Roof Nailing | Passed | Passed clip and nail 12/24/24 ok to proceed to intermediate | |
01/29/2025 | BULD - Electrical Clearance | Passed | 1/29/25 approval for TEP ECO clearence |