Permit: TC-MDP-0524-00653
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
6528 E CAMINO REBINA
Address NEW:
6528 E CAMINO REBINA
Apply Date:
05/27/2024
Applicant:
Christi Swenson
Description:
SFR PULT3513-2 T21-M0056
Permit Reviews
Permit Number - TC-MDP-0524-00653
Permit Status: Inspections complete
Permit Description: SFR PULT3513-2 T21-M0056
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/30/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 06/04/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0524-00653
Permit Status: Inspections complete
Permit Description: SFR PULT3513-2 T21-M0056
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 06/03/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 06/03/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 06/03/2024 | Post-Tension Inspection Report is required. |
| 06/03/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 06/03/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0524-00653
Permit Status: Inspections complete
Permit Description: SFR PULT3513-2 T21-M0056
| Date | Description | Comments |
|---|---|---|
| 05/24/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00653
Permite Description: SFR PULT3513-2 T21-M0056
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/10/2024 | COT - RSPL - Yard Water Line | N/A | Not Applicable | |
| 12/10/2024 | COT - RSEL - Electrical Final | N/A | Re-inspection required | Ac unit not level or on stable ground, external pvc must be painted, missing post tension tag. STOPPED INSPECTION-ADDITIONAL ITEMS MAY BE NOTED. |
| 12/10/2024 | COT - RSEL - Grounding/Bonding | N/A | Re-inspection required | Ac unit not level or on stable ground, external pvc must be painted, missing post tension tag. STOPPED INSPECTION-ADDITIONAL ITEMS MAY BE NOTED. |
| 12/10/2024 | COT - RSEL - Outdoor Lighting | N/A | Re-inspection required | Ac unit not level or on stable ground, external pvc must be painted, missing post tension tag. STOPPED INSPECTION-ADDITIONAL ITEMS MAY BE NOTED. |
| 12/10/2024 | COT - RSME - Mechanical Final | N/A | Re-inspection required | Ac unit not level or on stable ground, external pvc must be painted, missing post tension tag. STOPPED INSPECTION-ADDITIONAL ITEMS MAY BE NOTED. |
| 12/10/2024 | COT - RSPL - Plumbing Final | N/A | Re-inspection required | Ac unit not level or on stable ground, external pvc must be painted, missing post tension tag. STOPPED INSPECTION-ADDITIONAL ITEMS MAY BE NOTED. |
| 12/10/2024 | RSBU - Building Final | N/A | Re-inspection required | Ac unit not level or on stable ground, external pvc must be painted, missing post tension tag. STOPPED INSPECTION-ADDITIONAL ITEMS MAY BE NOTED. |
| 12/10/2024 | RSBU - Building Progress | N/A | Re-inspection required | Ac unit not level or on stable ground, external pvc must be painted, missing post tension tag. STOPPED INSPECTION-ADDITIONAL ITEMS MAY BE NOTED. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00653
Permit Description: SFR PULT3513-2 T21-M0056
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/24/2024 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading required. 6/24/2024 | |
| 06/24/2024 | COT - RSPL - Sewer | Passed | Okay to backfill. Shading required. 6/24/2024 | |
| 06/27/2024 | COT - RSBU - Preslab | Passed | ||
| 06/27/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 06/27/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 08/08/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Corrections were made. 8/8/2024 | |
| 08/08/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 08/27/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 8/27/2024 | |
| 09/05/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
| 09/09/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Corrections were made. 9/9/2024 | |
| 09/24/2024 | COT - RSBU - Interior Shear Bracing | Passed | pass 9/24/24 | |
| 11/13/2024 | COT - BULD - SWG Clearance | Passed | 11-13-24, approved for Southwest Gas connection. | |
| 12/10/2024 | ENGR Engineering Final | Passed | CO Ready | |
| 12/13/2024 | COT - RSEL - Electrical Final | Passed | 12/13/24 corrections made, no additional issues found. Passed final 12/13/24 CLEARANCE ECO | |
| 12/13/2024 | COT - RSEL - Grounding/Bonding | Passed | 12/13/24 corrections made, no additional issues found. Passed final 12/13/24 | |
| 12/13/2024 | COT - RSEL - Outdoor Lighting | Passed | 12/13/24 corrections made, no additional issues found. Passed final 12/13/24 | |
| 12/13/2024 | COT - RSME - Mechanical Final | Passed | 12/13/24 corrections made, no additional issues found. Passed final 12/13/24 | |
| 12/13/2024 | COT - RSPL - Plumbing Final | Passed | 12/13/24 corrections made, no additional issues found. Passed final 12/13/24 | |
| 12/13/2024 | RSBU - Building Final | Passed | 12/13/24 corrections made, no additional issues found. Passed final 12/13/24 | |
| 12/13/2024 | RSBU - Building Progress | Passed | 12/13/24 corrections made, no additional issues found. Passed final 12/13/24 |