Permit: TC-MDP-0524-00643
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
12769 E MEAGAN RIDGE PL
Address NEW:
12769 E MEAGAN RIDGE PL
Apply Date:
09/26/2024
Applicant:
Description:
SFR RKM45X T21-M0094 REVISION-Structural change
Permit Reviews
Permit Number - TC-MDP-0524-00643
Permit Status: Inspections complete
Permit Description: SFR RKM45X T21-M0094 REVISION-Structural change
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/21/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 10/29/2024 | APPROVED |
| 09/26/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 10/02/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0524-00643
Permit Status: Inspections complete
Permit Description: SFR RKM45X T21-M0094 REVISION-Structural change
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 05/17/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
| 09/27/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 09/27/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 09/27/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 09/27/2024 | Post-Tension Inspection Report is required. |
| 09/27/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0524-00643
Permit Status: Inspections complete
Permit Description: SFR RKM45X T21-M0094 REVISION-Structural change
| Date | Description | Comments |
|---|---|---|
| 10/21/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 05/17/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 09/27/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00643
Permite Description: SFR RKM45X T21-M0094 REVISION-Structural change
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/16/2024 | COT - RSBU - Roof Nailing | N/A | Canceled | 12-16-24, canceled per contractor. |
| 12/16/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Canceled | 12-16-24, canceled per contractor. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00643
Permit Description: SFR RKM45X T21-M0094 REVISION-Structural change
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2024 | COT - RSPL - Yard Water Line | Passed | 11-7-24, main water line inspection verified as per approved plans. Okay to backfill. | |
| 11/07/2024 | COT - RSPL - Sewer | Passed | 11-7-24, sewer connection verified as per approved plans. Okay to backfill. | |
| 11/07/2024 | COT - RSPL - Rough Soil | Passed | 11-7-24, underground plumbing verified as per approved plans. Okay to backfill. | |
| 11/14/2024 | COT - RSEL - Grounding/Bonding | Passed | 11-14-24, preslab, zoning/setbacks, ufer verified as per approved plans. Okay to pour concrete. | |
| 11/14/2024 | COT - RSBU - Preslab | Passed | 11-14-24, preslab, zoning/setbacks, ufer verified as per approved plans. Okay to pour concrete. | |
| 11/14/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 11-14-24, preslab, zoning/setbacks, ufer verified as per approved plans. Okay to pour concrete. | |
| 11/14/2024 | COT - RSEL - Electrical Underground | Passed | 11-14-24, preslab, zoning/setbacks, ufer verified as per approved plans. Okay to pour concrete. | |
| 12/17/2024 | COT - RSBU - Roof Nailing | Passed | 12/17/24 passed, corrections were made while on site. | |
| 12/17/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 12/17/24 king studs required at stairwell, corrections were made. Anchor bolts needed on west side of building. | |
| 01/22/2025 | COT - RSPL - Gas Pressure Test | Passed | 1/22/25 pass | |
| 01/23/2025 | BULD - Electrical Clearance | Passed | 1/22/25 approval for TEP ECO | |
| 02/06/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Passed by Tom pictures were received the day after initial inspection, all issues were corrected | |
| 02/06/2025 | COT - RSBU - Interior Shear Bracing | Passed | Passed interior shear inspection 2/6/25 ok to tape | |
| 03/24/2025 | COT - BULD - SWG Clearance | Passed | 3-24-25, Okay for SWG to install meter. Clearance issued. | |
| 04/15/2025 | COT - RSME - Mechanical Final | Passed | Passed final 4/15/25 | |
| 04/15/2025 | RSBU - Building Final | Passed | Passed final 4/15/25 | |
| 04/15/2025 | COT - RSEL - Outdoor Lighting | Passed | Passed final 4/15/25 | |
| 04/15/2025 | COT - RSPL - Plumbing Final | Passed | Passed final 4/15/25 | |
| 04/15/2025 | RSBU - Building Progress | Passed | Passed final 4/15/25 | |
| 04/15/2025 | COT - RSEL - Electrical Final | Passed | Passed final 4/15/25 | |
| 04/18/2025 | ENGR Engineering Final | Passed | Site is good. C of O ready. |