Permit: TC-MDP-0524-00641
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
12722 E MEAGAN RIDGE PL
Address NEW:
12722 E MEAGAN RIDGE PL
Apply Date:
05/28/2024
Applicant:
Andrea Flood
Description:
SFR RKM45X T21-M0094 REVISION-Structural change
Permit Reviews
Permit Number - TC-MDP-0524-00641
Permit Status: Inspections complete
Permit Description: SFR RKM45X T21-M0094 REVISION-Structural change
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/30/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 06/03/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0524-00641
Permit Status: Inspections complete
Permit Description: SFR RKM45X T21-M0094 REVISION-Structural change
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 05/17/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
| 06/03/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 06/03/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 06/03/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 06/03/2024 | Post-Tension Inspection Report is required. |
| 06/03/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0524-00641
Permit Status: Inspections complete
Permit Description: SFR RKM45X T21-M0094 REVISION-Structural change
| Date | Description | Comments |
|---|---|---|
| 05/17/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 06/03/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00641
Permite Description: SFR RKM45X T21-M0094 REVISION-Structural change
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/15/2024 | COT - RSBU - Interior Shear Bracing | N/A | Canceled | 11-15-24, cancelled by contractor |
| 02/03/2025 | RSBU - Building Final | N/A | Re-inspection required | Missing light at stairs 2/3/25 |
| 02/03/2025 | COT - RSEL - Electrical Final | N/A | Re-inspection required | Missing light at stairs 2/3/25 |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00641
Permit Description: SFR RKM45X T21-M0094 REVISION-Structural change
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/19/2024 | COT - RSPL - Sewer | Passed | ||
| 07/19/2024 | COT - RSPL - Rough Soil | Passed | ||
| 07/19/2024 | COT - RSPL - Backwater Valve | Passed | ||
| 07/19/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 07/30/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 07/30/2024 | COT - RSBU - Preslab | Passed | ||
| 07/30/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 07/30/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 08/23/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 08/23/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 10/29/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 10-29-24, intermediates approved. Okay to continue construction. | |
| 10/29/2024 | BULD - Electrical Clearance | Passed | 10-29-24, panel approved to be energized. | |
| 10/29/2024 | COT - RSPL - Gas Pressure Test | Passed | 10-29-24, gas pressure approved. | |
| 11/19/2024 | COT - RSBU - Interior Shear Bracing | Passed | 11-19-24, approved. Okay to tape & texture drywall. | |
| 01/10/2025 | COT - BULD - SWG Clearance | Passed | 1/10/25 passed CLEARANCE SWG | |
| 02/03/2025 | COT - RSEL - Outdoor Lighting | Passed | Passed final 2/3/25 | |
| 02/03/2025 | COT - RSME - Mechanical Final | Passed | Passed final 2/3/25 | |
| 02/03/2025 | COT - RSPL - Plumbing Final | Passed | Passed final 2/3/25 | |
| 02/03/2025 | RSBU - Building Progress | Passed | Passed final 2/3/25 | |
| 02/04/2025 | RSBU - Building Final | Passed | 2/4/25 corrections made | |
| 02/04/2025 | COT - RSEL - Electrical Final | Passed | 2/4/25 corrections made | |
| 04/11/2025 | ENGR Engineering Final | Passed |