Permit: TC-MDP-0524-00640
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
9817 E GRAY HAWK DR
Address NEW:
9817 E GRAY HAWK DR
Apply Date:
05/22/2024
Applicant:
Helen Ormsby
Description:
Casas del Cerrito H35B Plan
Permit Reviews
Permit Number - TC-MDP-0524-00640
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35B Plan
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/20/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/24/2025 | APPROVED |
| 05/23/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 05/29/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0524-00640
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35B Plan
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/17/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Conditions
Permit Number - TC-MDP-0524-00640
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35B Plan
| Date | Description | Comments |
|---|---|---|
| 05/28/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 05/28/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 05/17/2024 | Post-Tension Inspection Report is required. | |
| 05/17/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 05/28/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 05/28/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00640
Permite Description: Casas del Cerrito H35B Plan
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/06/2025 | COT - RSPL - Rough Soil | N/A | Re-inspection required | 01/06/25 Plumbing not per plan. Drain to laundry is 3'' per plan. Gray water is leaking at elbow. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00640
Permit Description: Casas del Cerrito H35B Plan
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/06/2025 | COT - RSPL - Backwater Valve | Passed | ||
| 01/06/2025 | COT - RSPL - Sewer | Passed | ||
| 01/06/2025 | COT - RSPL - Yard Water Line | Passed | Ok to backfill, shading required | |
| 01/14/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 1-14-25, preslab, electrical underground, bonding, excavation/setbacks approved. Okay to pour concrete. | |
| 01/14/2025 | COT - RSEL - Electrical Underground | Passed | 1-14-25, preslab, electrical underground, bonding, excavation/setbacks approved. Okay to pour concrete. | |
| 01/14/2025 | COT - RSBU - Preslab | Passed | 1-14-25, preslab, electrical underground, bonding, excavation/setbacks approved. Okay to pour concrete. | |
| 01/24/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Okay to proceed with rough in of mechanical, electrical, and plumbing work. | |
| 01/24/2025 | COT - RSBU - Roof Nailing | Passed | Okay to proceed with rough in of mechanical, electrical, and plumbing work. | |
| 01/29/2025 | BULD - Electrical Clearance | Passed | ECO Clearance issued to TEP for service at 9817 E. Gray Hawk Drive. | |
| 02/06/2025 | COT - RSEL - Grounding/Bonding | Passed | 2-6-25, approved | |
| 02/07/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 2/7/25: Holes in vapor barrier have been sealed with caulk. Mechanical, electrical, and plumbing rough-in is complete. Okay to proceed with insulation and drywall installation. | |
| 02/07/2025 | COT - RSPL - Gas Pressure Test | Passed | 2/7/25: Gas pressure test is at 15 psi for 10 minutes. Okay to proceed. | |
| 02/14/2025 | COT - RSBU - Interior Shear Bracing | Passed | 2/15/25: Drywall for interior shear drywall is properly secured to studs with screws per the plan requirements. Okay to proceed with tape, texture, and paint. | |
| 04/07/2025 | COT - BULD - SWG Clearance | Passed | Passed CLEARANCE SWG 4/7/25 | |
| 04/16/2025 | COT - RSEL - Electrical Final | Passed | Passed final 4/16/25 | |
| 04/16/2025 | COT - RSEL - Outdoor Lighting | Passed | Passed final 4/16/25 | |
| 04/16/2025 | COT - RSME - Mechanical Final | Passed | Passed final 4/16/25 | |
| 04/16/2025 | COT - RSPL - Plumbing Final | Passed | Passed final 4/16/25 | |
| 04/16/2025 | ENGR Engineering Final | Passed | ||
| 04/16/2025 | RSBU - Building Final | Passed | Passed final 4/16/25 | |
| 04/16/2025 | RSBU - Building Progress | Passed | Passed final 4/16/25 |