Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address NEW:
9817 E GRAY HAWK DR
Apply Date:
05/22/2024
Applicant:
Helen Ormsby
Description:
Casas del Cerrito H35B Plan

Permit Reviews

Permit Number - TC-MDP-0524-00640
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35B Plan
Start Date Submittal Complete Date Status  
02/20/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/24/2025 APPROVED Review Details
05/23/2024 SITE FROM MODEL PERMIT - SUBDIVISION v.1 05/29/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0524-00640
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35B Plan
Total Outstanding Activity Conditions - 1
Date Name
05/17/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.

Conditions

Permit Number - TC-MDP-0524-00640
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35B Plan
Date Description Comments
05/28/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
05/28/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
05/17/2024 Post-Tension Inspection Report is required.
05/17/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
05/28/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
05/28/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00640
Permite Description: Casas del Cerrito H35B Plan
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
01/06/2025 COT - RSPL - Rough Soil N/A Re-inspection required 01/06/25

Plumbing not per plan. Drain to laundry is 3'' per plan.
Gray water is leaking at elbow.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00640
Permit Description: Casas del Cerrito H35B Plan
Total Completed Inspections - 21
Date Description Inspector Results Comments
01/06/2025 COT - RSPL - Backwater Valve Passed
01/06/2025 COT - RSPL - Sewer Passed
01/06/2025 COT - RSPL - Yard Water Line Passed Ok to backfill, shading required
01/14/2025 COT - RSBU - Excavation/Rebar/Zoning Passed 1-14-25, preslab, electrical underground, bonding, excavation/setbacks approved. Okay to pour concrete.
01/14/2025 COT - RSEL - Electrical Underground Passed 1-14-25, preslab, electrical underground, bonding, excavation/setbacks approved. Okay to pour concrete.
01/14/2025 COT - RSBU - Preslab Passed 1-14-25, preslab, electrical underground, bonding, excavation/setbacks approved. Okay to pour concrete.
01/24/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Okay to proceed with rough in of mechanical, electrical, and plumbing work.
01/24/2025 COT - RSBU - Roof Nailing Passed Okay to proceed with rough in of mechanical, electrical, and plumbing work.
01/29/2025 BULD - Electrical Clearance Passed ECO Clearance issued to TEP for service at 9817 E. Gray Hawk Drive.
02/06/2025 COT - RSEL - Grounding/Bonding Passed 2-6-25, approved
02/07/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 2/7/25: Holes in vapor barrier have been sealed with caulk. Mechanical, electrical, and plumbing rough-in is complete. Okay to proceed with insulation and drywall installation.
02/07/2025 COT - RSPL - Gas Pressure Test Passed 2/7/25: Gas pressure test is at 15 psi for 10 minutes. Okay to proceed.
02/14/2025 COT - RSBU - Interior Shear Bracing Passed 2/15/25: Drywall for interior shear drywall is properly secured to studs with screws per the plan requirements. Okay to proceed with tape, texture, and paint.
04/07/2025 COT - BULD - SWG Clearance Passed Passed CLEARANCE SWG 4/7/25
04/16/2025 COT - RSEL - Electrical Final Passed Passed final 4/16/25
04/16/2025 COT - RSEL - Outdoor Lighting Passed Passed final 4/16/25
04/16/2025 COT - RSME - Mechanical Final Passed Passed final 4/16/25
04/16/2025 COT - RSPL - Plumbing Final Passed Passed final 4/16/25
04/16/2025 ENGR Engineering Final Passed
04/16/2025 RSBU - Building Final Passed Passed final 4/16/25
04/16/2025 RSBU - Building Progress Passed Passed final 4/16/25

Documents

File Name Document Type  
CDC 17 SIC-2025-02-20_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CDC 17 D1_V1.PDF DOCUMENTS VIEW
CDC 17 SIC-2024-05-22_V1.PDF DOCUMENTS VIEW