Permit: TC-MDP-0524-00605
Permit Details
Apply Date:
05/10/2024
Applicant:
Cindy Nemo
Description:
Blackhawk T936 - Palm
Permit Reviews
Permit Number - TC-MDP-0524-00605
Permit Status: Issued
Permit Description: Blackhawk T936 - Palm
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/13/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 05/28/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0524-00605
Permit Status: Issued
Permit Description: Blackhawk T936 - Palm
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
05/10/2024 | Post-Tension Inspection Report is required. |
05/15/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
05/15/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
05/15/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0524-00605
Permit Status: Issued
Permit Description: Blackhawk T936 - Palm
Date | Description | Comments |
---|---|---|
05/28/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
05/10/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
05/10/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
05/15/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-MDP-0524-00605
Permite Description: Blackhawk T936 - Palm
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/12/2025 | ENGR Engineering Final | N/A | Not Ready | Concrete footing at gate needs to be finished being removed. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-MDP-0524-00605
Permit Description: Blackhawk T936 - Palm
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/13/2024 | COT - RSPL - Backwater Valve | Passed | Okay to backfill. Shading required. 8/13/2024 | |
08/13/2024 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading required. 8/13/2024 | |
08/13/2024 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading required. 8/13/2024 | |
08/13/2024 | COT - RSPL - Sewer | Passed | Okay to backfill. Shading required. 8/13/2024 | |
08/20/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
08/20/2024 | COT - RSBU - Preslab | Passed | ||
08/20/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
08/20/2024 | COT - RSEL - Electrical Underground | Passed | ||
09/13/2024 | COT - RSBU - Roof Nailing | Passed | ||
09/24/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | Corrections were made. 9/24/2024 | |
10/23/2024 | BULD - Electrical Clearance | Passed | 10-23-24, approved for electrical clearance. | |
10/23/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 10-23-24, intermediates approved. | |
10/23/2024 | COT - RSPL - Gas Pressure Test | Passed | 10-23-24, gas pressure test approved. | |
11/06/2024 | COT - RSBU - Interior Shear Bracing | Passed | 11-6-24, interior shear wall inspection approved. Okay to tape & texture drywall. | |
12/06/2024 | RSBU - Building Progress | Passed | 12-6-24, okay to pour entryway. | |
01/27/2025 | COT - BULD - SWG Clearance | Passed | approval for SWG clearance. | |
01/27/2025 | COT - RSEL - Outdoor Lighting | Passed | 1/27/25 pass | |
01/27/2025 | COT - RSPL - Plumbing Final | Passed | 1/27/25 pass | |
02/12/2025 | COT - RSME - Mechanical Final | Passed | 2/12/25 corrections made | |
02/12/2025 | COT - RSEL - Electrical Final | Passed | 2/12/25 corrections made CLEARANCE ECO | |
02/12/2025 | RSBU - Building Final | Passed | 2/12/25 corrections made |