Permit: TC-MDP-0524-00589
Permit Details
Apply Date:
05/02/2024
Applicant:
Description:
VC 1262-130
Permit Reviews
Permit Number - TC-MDP-0524-00589
Permit Status: Inspections complete
Permit Description: VC 1262-130
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/21/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.2 | 06/24/2024 | APPROVED |
06/14/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 06/14/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-MDP-0524-00589
Permit Status: Inspections complete
Permit Description: VC 1262-130
Total Outstanding Activity Conditions - 6
Date | Name |
---|---|
05/02/2024 | Post-Tension Inspection Report is required. |
05/02/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
05/02/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
06/24/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
06/24/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
06/24/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0524-00589
Permit Status: Inspections complete
Permit Description: VC 1262-130
Date | Description | Comments |
---|---|---|
05/02/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0524-00589
Permit Description: VC 1262-130
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/05/2024 | COT - RSPL - Rough Soil | Passed | ||
07/05/2024 | COT - RSPL - Sewer | Passed | ||
07/17/2024 | COT - RSBU - Preslab | Passed | ||
07/17/2024 | COT - RSEL - Electrical Underground | Passed | ||
07/17/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
07/17/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
08/13/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
08/13/2024 | COT - RSBU - Roof Nailing | Passed | ||
08/30/2024 | COT - RSPL - Yard Water Line | Passed | ||
09/03/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
09/04/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Corrections were made. 9/4/2024 | |
09/13/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 9/13/2024 | |
10/03/2024 | COT - RSBU - Interior Shear Bracing | Passed | PASSED SHEER WALL BRACING 10/3/2024 | |
10/16/2024 | COT - BULD - SWG Clearance | Passed | PASSED SW GAS CLEARANCE 10/16/24 | |
11/20/2024 | ENGR Engineering Final | Passed | CO Ready | |
11/25/2024 | COT - RSEL - Electrical Final | Passed | 11-25-24, electrical, mechanical,plumbing, outdoor lighting and building finals all approved. | |
11/25/2024 | COT - RSEL - Outdoor Lighting | Passed | 11-25-24, electrical, mechanical,plumbing, outdoor lighting and building finals all approved. | |
11/25/2024 | COT - RSME - Mechanical Final | Passed | 11-25-24, electrical, mechanical,plumbing, outdoor lighting and building finals all approved. | |
11/25/2024 | COT - RSPL - Plumbing Final | Passed | 11-25-24, electrical, mechanical,plumbing, outdoor lighting and building finals all approved. | |
11/25/2024 | RSBU - Building Final | Passed | 11-25-24, electrical, mechanical,plumbing, outdoor lighting and building finals all approved. | |
11/25/2024 | RSBU - Building Progress | Passed | 11-25-24, electrical, mechanical,plumbing, outdoor lighting and building finals all approved. |