Permit: TC-MDP-0523-01102
Permit Details
Apply Date:
05/30/2023
Applicant:
HSLCS Permits
Description:
Building B three-story, 24 unit, apartment building model plans
Permit Reviews
Permit Number - TC-MDP-0523-01102
Permit Status: Complete
Permit Description: Building B three-story, 24 unit, apartment building model plans
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/27/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/24/2023 | APPROVED |
08/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 08/20/2024 | APPROVED |
10/01/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/01/2024 | APPROVED |
07/05/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/08/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-MDP-0523-01102
Permit Status: Complete
Permit Description: Building B three-story, 24 unit, apartment building model plans
Date | Description | Comments |
---|---|---|
08/20/2024 | AIR BALANCING REPORT IS REQUIRED. | |
04/21/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
04/21/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
04/21/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
04/21/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
05/30/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/21/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
08/20/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0523-01102
Permite Description: Building B three-story, 24 unit, apartment building model plans
Total Outstanding Inspections - 7
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/30/2024 | COT - LCBU - Exterior Clips/Sheathing | N/A | Not Ready | 11/28/23: 1st level 12/12/23: 3rd level deck (east half) 1/30/24: not ready |
02/16/2024 | COT - LCBU - Framing | N/A | Partial Pass | Good to go. Partial-pass. |
10/02/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
10/02/2024 | COT - LCPL - Gas Pressure Test | N/A | Not Applicable | |
10/04/2024 | COT - LCEL - Electrical Final | N/A | Partial Pass | 10/4/2024 partial pass for north tower. |
10/04/2024 | COT - LCPL - Plumbing Final | N/A | Partial Pass | 10/4/2024 partial pass for north tower. |
10/04/2024 | COT - LCME - Mechanical Final | N/A | Partial Pass | 10/4/2024 partial pass for north tower. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0523-01102
Permit Description: Building B three-story, 24 unit, apartment building model plans
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/07/2023 | COT - LCPL - Rough Soil | Passed | Building #2 Underground plumbing is complete and under a water test. Okay to shade piping and backfill trenches. | |
08/23/2023 | COT - LCPL - Yard Water Line | Passed | ||
08/31/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | Note: Informed builder of weep screed requirements.. | |
08/31/2023 | COT - LCBU - Preslab | Passed | Note: Informed builder of weep screed requirements.. | |
08/31/2023 | COT - LCEL - Electrical Underground | Passed | ||
08/31/2023 | COT - LCEL - Grounding/Bonding | Passed | ||
01/29/2024 | COT - LCBU - Roof Nailing | Passed | 11/16/23: 2nd floor deck nailing approved. 12/15/23: 3rd floor deck nailing approved Westside. 1/26/24: not ready 1/29/24: roof nailing approved ok to dry-In |
|
02/16/2024 | COT - LCPL - Sewer | Passed | ||
04/24/2024 | COT - LCBU - Exterior Clips/Sheathing | Passed | ||
05/20/2024 | COT - HCPL - Plumbing Roof Drains | Passed | ||
05/20/2024 | COT - LCME - Mechanical Intermediate | Passed | 5/13/24: third floor passed. 5/20/24: second floor passed |
|
05/29/2024 | COT - LCPL - Plumbing Intermediate | Passed | ||
05/29/2024 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
05/29/2024 | COT - LCME - Mechanical Above Ceiling | Passed | ||
05/29/2024 | COT - LCEL - Electrical Intermediate | Passed | ||
05/29/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
05/29/2024 | COT - LCBU - Framing | Passed | ||
06/10/2024 | COT - LCBU - Building Above Ceiling | Passed | ||
06/13/2024 | COT - HCBU - Interior Shear Bracing | Passed | ||
07/25/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. BUILDING #2. SERVCE #1 NORTHEAST, UNITS #2304,#2301,#2201,#2101,#2204,HOUSE PANEL,#2104,#2302,#2202,#2102,#2303,#2203,#2103. SERVICE #2. NORTHWEST, UNITS #2308,#2305,#2208,#2108,#2306,#2206,#2205,#2105,#2307,#2207,#2106,#2107. 7/25/2024 |
|
09/17/2024 | COT - FCON - Fire - Final | Passed | ||
10/07/2024 | COT - LCEL - Electrical Final | Passed | 10/7/2024 partial pass. West tower approved. | |
10/09/2024 | COT - LCPL - Plumbing Final | Passed | ||
10/09/2024 | COT - LCME - Mechanical Final | Passed | ||
10/15/2024 | TRSP - ROW - Final/Close-Out | Passed | right of way work complete site closed | |
10/16/2024 | COT - LCBU - Building Final | Passed | ||
10/16/2024 | COT - LCEL - Outdoor Lighting | Passed | ||
10/16/2024 | ENGR Engineering Final | Passed | We will relook at the basin on the north west corner when doing the engineering final for Bld. 4 |