Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
05/30/2023
Applicant:
HSLCS Permits
Description:
Building B three-story, 24 unit, apartment building model plans

Permit Reviews

Permit Number - TC-MDP-0523-01102
Permit Status: Complete
Permit Description: Building B three-story, 24 unit, apartment building model plans
Start Date Submittal Complete Date Status  
06/27/2023 COMMERCIAL REVIEW - FULL v.1 07/24/2023 APPROVED Review Details
08/15/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 08/20/2024 APPROVED Review Details
10/01/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/01/2024 APPROVED Review Details
07/05/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/08/2024 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-MDP-0523-01102
Permit Status: Complete
Permit Description: Building B three-story, 24 unit, apartment building model plans
Date Description Comments
08/20/2024 AIR BALANCING REPORT IS REQUIRED.
04/21/2023 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
04/21/2023 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/21/2023 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
04/21/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
05/30/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
04/21/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
08/20/2024 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0523-01102
Permite Description: Building B three-story, 24 unit, apartment building model plans
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
01/30/2024 COT - LCBU - Exterior Clips/Sheathing N/A Not Ready 11/28/23: 1st level
12/12/23: 3rd level deck (east half)
1/30/24: not ready
02/16/2024 COT - LCBU - Framing N/A Partial Pass Good to go. Partial-pass.
10/02/2024 COT - BULD - SWG Clearance N/A Not Applicable
10/02/2024 COT - LCPL - Gas Pressure Test N/A Not Applicable
10/04/2024 COT - LCEL - Electrical Final N/A Partial Pass 10/4/2024 partial pass for north tower.
10/04/2024 COT - LCPL - Plumbing Final N/A Partial Pass 10/4/2024 partial pass for north tower.
10/04/2024 COT - LCME - Mechanical Final N/A Partial Pass 10/4/2024 partial pass for north tower.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0523-01102
Permit Description: Building B three-story, 24 unit, apartment building model plans
Total Completed Inspections - 28
Date Description Inspector Results Comments
08/07/2023 COT - LCPL - Rough Soil Passed Building #2 Underground plumbing is complete and under a water test. Okay to shade piping and backfill trenches.
08/23/2023 COT - LCPL - Yard Water Line Passed
08/31/2023 COT - LCBU - Excavation/Rebar/Zoning Passed Note: Informed builder of weep screed requirements..
08/31/2023 COT - LCBU - Preslab Passed Note: Informed builder of weep screed requirements..
08/31/2023 COT - LCEL - Electrical Underground Passed
08/31/2023 COT - LCEL - Grounding/Bonding Passed
01/29/2024 COT - LCBU - Roof Nailing Passed 11/16/23: 2nd floor deck nailing approved.
12/15/23: 3rd floor deck nailing approved Westside.
1/26/24: not ready
1/29/24: roof nailing approved ok to dry-In
02/16/2024 COT - LCPL - Sewer Passed
04/24/2024 COT - LCBU - Exterior Clips/Sheathing Passed
05/20/2024 COT - HCPL - Plumbing Roof Drains Passed
05/20/2024 COT - LCME - Mechanical Intermediate Passed 5/13/24: third floor passed.
5/20/24: second floor passed
05/29/2024 COT - LCPL - Plumbing Intermediate Passed
05/29/2024 COT - LCPL - Plumbing Above Ceiling Passed
05/29/2024 COT - LCME - Mechanical Above Ceiling Passed
05/29/2024 COT - LCEL - Electrical Intermediate Passed
05/29/2024 COT - LCEL - Electrical Above Ceiling Passed
05/29/2024 COT - LCBU - Framing Passed
06/10/2024 COT - LCBU - Building Above Ceiling Passed
06/13/2024 COT - HCBU - Interior Shear Bracing Passed
07/25/2024 BULD - Electrical Clearance Passed Clearance for TEP ECO. BUILDING #2. SERVCE #1 NORTHEAST, UNITS #2304,#2301,#2201,#2101,#2204,HOUSE PANEL,#2104,#2302,#2202,#2102,#2303,#2203,#2103.

SERVICE #2. NORTHWEST, UNITS #2308,#2305,#2208,#2108,#2306,#2206,#2205,#2105,#2307,#2207,#2106,#2107. 7/25/2024
09/17/2024 COT - FCON - Fire - Final Passed
10/07/2024 COT - LCEL - Electrical Final Passed 10/7/2024 partial pass. West tower approved.
10/09/2024 COT - LCPL - Plumbing Final Passed
10/09/2024 COT - LCME - Mechanical Final Passed
10/15/2024 TRSP - ROW - Final/Close-Out Passed right of way work complete site closed
10/16/2024 COT - LCBU - Building Final Passed
10/16/2024 COT - LCEL - Outdoor Lighting Passed
10/16/2024 ENGR Engineering Final Passed We will relook at the basin on the north west corner when doing the engineering final for Bld. 4

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
EES_240925_WATER_CHLORINATION_REPORT_BLDG2-2024-10-01_V1.PDF DOCUMENTS VIEW
EES_240927_AIR_BALANCE_REPORT_BLDG2_V1.PDF DOCUMENTS VIEW
EES_240812_SIC_FINAL_BLDG2_COMBINED-2024-08-12_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
EES_210223_GEOTECH_REPORT_V1.PDF DOCUMENTS VIEW
EES_230530_BUILDINGS_2_SIC-2023-06-16_V1.PDF DOCUMENTS VIEW
EES_230616_ SITE PLANS (BLDG 2)_V1.PDF DOCUMENTS VIEW