Permit: TC-MDP-0523-01096
Permit Details
Apply Date:
05/29/2023
Applicant:
HSLCS Permits
Description:
Building A two-story, 16 unit, apartment building model plans.
Permit Reviews
Permit Number - TC-MDP-0523-01096
Permit Status: Complete
Permit Description: Building A two-story, 16 unit, apartment building model plans.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/02/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/03/2024 | REQUIRES RESUBMIT |
08/05/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 08/08/2024 | APPROVED |
06/29/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/24/2023 | APPROVED |
11/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/18/2024 | APPROVED |
11/19/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/19/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0523-01096
Permit Status: Complete
Permit Description: Building A two-story, 16 unit, apartment building model plans.
Date | Description | Comments |
---|---|---|
08/08/2024 | AIR BALANCING REPORT IS REQUIRED. | |
04/19/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
04/19/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
04/19/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
05/30/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/19/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
08/08/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0523-01096
Permite Description: Building A two-story, 16 unit, apartment building model plans.
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/01/2024 | COT - LCBU - Roof Nailing | N/A | Partial Pass | Ceiling/floor good to go. Partial-pass. Ok to proceed. 2/1/24: roof nailing at field passed ok to proceed. |
02/13/2024 | COT - LCBU - Framing | N/A | Partial Pass | 2/13/24: RFI will be required for missing holdowns (H3 missing at first floor), framing inspection complete. |
COT - FCON - Fire - Final | N/A | Not Ready | need to test fire alarm | |
11/07/2024 | COT - LCEL - Electrical Final | N/A | Re-inspection required | 11/7/24: unit 11207 incomplete plumbing fixtures and GFCI in laundry not working properly, unit 11104 Lav at bathroom missing, 11204 clean out cap at laundry required, 11206 leak at bathroom lav. Pending south tower, exterior and roof. |
11/07/2024 | COT - LCME - Mechanical Final | N/A | Re-inspection required | 11/7/24: unit 11207 incomplete plumbing fixtures and GFCI in laundry not working properly, unit 11104 Lav at bathroom missing, 11204 clean out cap at laundry required, 11206 leak at bathroom lav. Pending south tower, exterior and roof. |
11/07/2024 | COT - LCPL - Plumbing Final | N/A | Re-inspection required | 11/7/24: unit 11207 incomplete plumbing fixtures and GFCI in laundry not working properly, unit 11104 Lav at bathroom missing, 11204 clean out cap at laundry required, 11206 leak at bathroom lav. Pending south tower |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0523-01096
Permit Description: Building A two-story, 16 unit, apartment building model plans.
Total Completed Inspections - 30
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/12/2023 | COT - LCPL - Rough Soil | Passed | ||
10/25/2023 | PDSD Building Division - Unspecified In-Field | Passed | Footings for both halves of building #11 are properly dug, rebar reinforcement is installed along with post tension cabling. All H.3 clips and MASA Clips are installed per plans and specifications. All plumbing pipes are properly wrapped to protect from concrete damage. | |
10/25/2023 | COT - LCBU - Preslab | Passed | Footings for both halves of building #11 are properly dug, rebar reinforcement is installed along with post tension cabling. All H.3 clips and MASA Clips are installed per plans and specifications. All plumbing pipes are properly wrapped to protect from concrete damage. okay to pour concrete slab. | |
10/25/2023 | COT - LCEL - Electrical Underground | Passed | Conduit for Underground electrical for cameras to clubhouse, light poles around building, and kitchen islands have all been installed. | |
10/25/2023 | COT - LCEL - Grounding/Bonding | Passed | Ufer ground is in place on both halves with #6 bare copper wire attached to Ufer and buried in concrete pour. | |
02/07/2024 | COT - LCBU - Exterior Clips/Sheathing | Passed | Level 1 clips and sheathing good to go. 2/7/24: exterior clips and sheathing from level 1 to level 2 per plan ok to proceed. |
|
02/09/2024 | COT - LCBU - Roof Nailing | Passed | ||
02/22/2024 | COT - LCPL - Sewer | Passed | 2/22/24: HCS connection complete ok to backfill. Shading required. | |
05/17/2024 | COT - LCPL - Yard Water Line | Passed | ||
06/13/2024 | COT - LCBU - Building Above Ceiling | Passed | ||
06/13/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
06/13/2024 | COT - LCME - Mechanical Above Ceiling | Passed | ||
06/13/2024 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
06/17/2024 | COT - LCBU - Framing | Passed | 2/13/24: RFI will be required for missing holdowns (H3 missing at first floor), framing inspection complete. 6/12/24: not ready 6/12/24: not ready 6/13/24: 2nd floor intermediates passed. Ok to proceed 6/17/24: 1st floor intermediates passed ok to proceed. |
|
06/17/2024 | COT - LCME - Mechanical Intermediate | Passed | 2/13/24: RFI will be required for missing holdowns (H3 missing at first floor), framing inspection complete. 6/12/24: not ready 6/12/24: not ready 6/13/24: 2nd floor intermediates passed. Ok to proceed 6/17/24: 1st floor intermediates passed ok to proceed. |
|
06/17/2024 | COT - LCPL - Plumbing Intermediate | Passed | ||
06/17/2024 | COT - HCBU - Masonry Pregrout | Passed | ||
06/17/2024 | COT - LCEL - Electrical Intermediate | Passed | 2/13/24: RFI will be required for missing holdowns (H3 missing at first floor), framing inspection complete. 6/12/24: not ready 6/12/24: not ready 6/13/24: 2nd floor intermediates passed. Ok to proceed 6/17/24: 1st floor intermediates passed ok to proceed. |
|
07/22/2024 | COT - HCBU - Interior Shear Bracing | Passed | ||
09/13/2024 | COT - BULD - SWG Clearance | Passed | ||
09/13/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. BUILDING #11. NORTHSIDE METERS. #11206,11205,11108,11106,11208,11207,11107,111105. SOUTHSIDE METER. #11201,11204,11101,11203,11104,11103,EV CHARGE STATION,11202,11102,AND HOUSE PANEL. 9/13/2024 |
|
09/13/2024 | COT - LCPL - Gas Pressure Test | Passed | ||
11/20/2024 | COT - FCON - Fire - Final | Passed | ||
11/20/2024 | COT - LCEL - Electrical Final | Passed | ||
11/20/2024 | COT - LCME - Mechanical Final | Passed | ||
11/21/2024 | TRSP - ROW - Final/Close-Out | Passed | no impact to right of way | |
11/20/2024 | COT - LCEL - Outdoor Lighting | Passed | ||
11/21/2024 | COT - LCPL - Plumbing Final | Passed | ||
11/22/2024 | ENGR Engineering Final | Passed | CO Ready | |
11/22/2024 | COT - LCBU - Building Final | Passed | 11/7/24: unit 11207 incomplete plumbing fixtures and GFCI in laundry not working properly, unit 11104 Lav at bathroom missing, 11204 clean out cap at laundry required, 11206 leak at bathroom lav. Pending south tower 11/20/24: pending 11104, and roof 11/21/24: ok for level 4 TCO 11/22/24: ok for CofO |