Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
05/29/2023
Applicant:
Erin Dick
Description:
Building A two-story, 16 unit, apartment building model plans.

Permit Reviews

Permit Number - TC-MDP-0523-01093
Permit Status: Inspections complete
Permit Description: Building A two-story, 16 unit, apartment building model plans.
Start Date Submittal Complete Date Status  
01/17/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/21/2025 APPROVED Review Details
06/28/2023 COMMERCIAL REVIEW - FULL v.1 07/24/2023 APPROVED Review Details
08/29/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 09/01/2024 APPROVED Review Details
07/02/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/03/2024 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0523-01093
Permit Status: Inspections complete
Permit Description: Building A two-story, 16 unit, apartment building model plans.
Total Outstanding Activity Conditions - 1
Date Name
09/01/2024 COMMISSIONING REPORT IS REQUIRED.

Conditions

Permit Number - TC-MDP-0523-01093
Permit Status: Inspections complete
Permit Description: Building A two-story, 16 unit, apartment building model plans.
Date Description Comments
09/01/2024 AIR BALANCING REPORT IS REQUIRED.
04/19/2023 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/19/2023 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
04/19/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
05/30/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
04/19/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
09/01/2024 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0523-01093
Permite Description: Building A two-story, 16 unit, apartment building model plans.
Total Outstanding Inspections - 15
Last Inspection Date Description Inspector Results Comments
01/03/2024 COT - LCBU - Preslab N/A Partial Pass 1/3/23: pending breezeway.
01/03/2024 COT - LCBU - Excavation/Rebar/Zoning N/A Partial Pass 1/3/23: pending breezeway.
03/01/2024 COT - LCBU - Exterior Clips/Sheathing N/A Partial Pass 3/1/24: first floor exterior clip and sheathing passed. pending framing inspection
05/17/2024 COT - LCPL - Yard Water Line N/A Canceled
07/31/2024 COT - LCPL - Gas Pressure Test N/A Not Applicable
07/31/2024 COT - LCEL - Electrical Above Ceiling N/A Not Ready 6/12/24: not ready
6/26/24: partial pass at landings and breezeways ok to proceed.
6/4/24: not ready
7/31/24: not ready
07/31/2024 COT - LCME - Mechanical Above Ceiling N/A Not Ready 6/12/24: not ready
6/26/24: partial pass at landings and breezeways ok to proceed.
6/4/24: not ready
7/31/24: not ready
07/31/2024 COT - LCBU - Building Above Ceiling N/A Not Ready 7/31/24: not ready
08/01/2024 COT - BULD - SWG Clearance N/A Not Applicable
03/04/2024 COT - LCBU - Framing N/A Partial Pass 3/4/24: first floor framing per plan ok to proceed.
07/31/2024 COT - LCPL - Plumbing Intermediate N/A Not Ready 6/4/24: not ready
7/31/24: not ready
08/12/2024 COT - LCPL - Plumbing Roof Drains N/A Not Ready 8/12/24: not ready
08/12/2024 COT - LCME - Mechanical Intermediate N/A Partial Pass 8/12/24: Stud at girder trust in three units need to be added.
08/12/2024 COT - LCEL - Electrical Intermediate N/A Partial Pass 8/12/24: second floor passed.
10/17/2024 BULD - Electrical Clearance N/A Not Applicable

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0523-01093
Permit Description: Building A two-story, 16 unit, apartment building model plans.
Total Completed Inspections - 26
Date Description Inspector Results Comments
09/29/2023 COT - LCPL - Rough Soil Passed
01/03/2024 COT - LCEL - Electrical Underground Passed
01/03/2024 COT - LCEL - Grounding/Bonding Passed
02/15/2024 COT - LCPL - Sewer Passed 2/15/24: HCS connection made and approved. Ok to backfill. Shading required
04/08/2024 COT - LCBU - Roof Nailing Passed
04/10/2024 COT - LCBU - Exterior Clips/Sheathing Passed
06/04/2024 COT - LCPL - Yard Water Line Passed 3/25/24: partial pass 15' run pending point of connection to back flow preventer and main.
6/4/24: connection to main and back flow preventer made. Ok to backfill shading required
08/01/2024 COT - LCEL - Electrical Above Ceiling Passed
08/01/2024 COT - LCME - Mechanical Above Ceiling Passed
08/01/2024 COT - LCBU - Building Above Ceiling Passed
08/01/2024 COT - LCPL - Plumbing Above Ceiling Passed
08/05/2024 COT - LCBU - Framing Passed 3/4/24: first floor framing per plan ok to proceed.
6/12/24: not ready
6/26/24: partial pass at landings and breezeways ok to proceed.
6/4/24: not ready
7/31/24: not ready
8/5/24: first floor passed.
08/05/2024 COT - LCPL - Plumbing Intermediate Passed 3/4/24: first floor framing per plan ok to proceed.
6/12/24: not ready
6/26/24: partial pass at landings and breezeways ok to proceed.
6/4/24: not ready
7/31/24: not ready
8/5/24: first floor passed.
08/15/2024 COT - LCPL - Plumbing Roof Drains Passed
08/15/2024 COT - LCME - Mechanical Intermediate Passed
08/15/2024 COT - LCEL - Electrical Intermediate Passed
09/09/2024 COT - HCBU - Interior Shear Bracing Passed
10/31/2024 BULD - Electrical Clearance Passed 10/31/24: TEP ECO CLEARANCE FOR 7355VS WILMOT RD BLDG 7 UNITS 7105,7106,7107,7108,7205,7206,7207,7208,7204,7203,7202,7201,7104,7102,7101,7103, House Panel, Spare,
01/13/2025 COT - FCON - Fire - Final Passed
01/24/2025 COT - LCPL - Plumbing Final Passed
01/24/2025 COT - LCME - Mechanical Final Passed
01/24/2025 COT - LCEL - Electrical Final Passed
01/24/2025 COT - LCEL - Outdoor Lighting Passed
01/24/2025 TRSP - ROW - Final/Close-Out Passed
01/24/2025 ENGR Engineering Final Passed Drainage pipe on the south side needs the ends cleaned out.
Move the tree in front of the meters at least another 2' away from them.
Re-stretch the artificial turf in the front to eliminate all trip hazards.
Clean out the 8' pipe in the front.
01/24/2025 COT - LCBU - Building Final Passed

Documents

File Name Document Type  
EES_250107_WATER_CHLORINATION_REPORT_BLDG7-2025-01-10_V1.PDF DOCUMENTS VIEW
EES_250111_AIR_BALANCE_REPORT_BLDG7_V1.PDF DOCUMENTS VIEW
EES_240828_SIC_FINAL_BLDG7_COMBINED-2024-08-28_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
EES_210223_GEOTECH_REPORT_V1.PDF DOCUMENTS VIEW
EES_230530_BUILDING_7_SPECIAL INSPECTION CERT-2023-06-20_V1.PDF DOCUMENTS VIEW
EES_230620_ SITE PLANS (BLDG 7)_V1.PDF DOCUMENTS VIEW