Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0523-01070
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
12812 E TORTOISE POINTE PL
Address NEW:
12812 E TORTOISE POINTE PL
Apply Date:
06/06/2023
Applicant:
Amy Stokes, Operations Accountant
Description:
SFR RKF55F T21-M0087
Permit Reviews
Permit Number - TC-MDP-0523-01070
Permit Status: Inspections complete
Permit Description: SFR RKF55F T21-M0087
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/20/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/20/2023 | APPROVED |
| 06/16/2023 | ZZZMODEL PERMIT REVIEW RESIDENTIAL v.2 | 06/20/2023 | APPROVED |
| 06/08/2023 | ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 | 06/13/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-MDP-0523-01070
Permit Status: Inspections complete
Permit Description: SFR RKF55F T21-M0087
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/20/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0523-01070
Permit Status: Inspections complete
Permit Description: SFR RKF55F T21-M0087
| Date | Description | Comments |
|---|---|---|
| 06/10/2023 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. | |
| 06/08/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 06/08/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 12/20/2023 | NO FINAL UNTIL THE DISCHARGE AUTHORIZATIONFOR #P21SD00033 IS ISSUED BY PDEQ | |
| 12/20/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 01/20/2023 | Post-Tension Inspection Report is required. | |
| 05/25/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 06/08/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0523-01070
Permite Description: SFR RKF55F T21-M0087
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/02/2023 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Not Applicable | |
| 11/16/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | 11/16/23: post 3 framing members under each end of 3-ply girder truss, gas pressure at 4 psi, every register is unblocked, burn in line-sets, AC platform is uneven in the middle with blocking too high or too low, remove air admittance valve in laundry room and vent thru roof per approved plans, INSPECTION STOPPED. MORE ITEMS MAY BE ADDED AT NEXT INSPECTION. |
| 11/16/2023 | COT - RSPL - Gas Pressure Test | N/A | Re-inspection required | 11/16/23: post 3 framing members under each end of 3-ply girder truss, gas pressure at 4 psi, every register is unblocked, burn in line-sets, AC platform is uneven in the middle with blocking too high or too low, remove air admittance valve in laundry room and vent thru roof per approved plans, INSPECTION STOPPED. MORE ITEMS MAY BE ADDED AT NEXT INSPECTION. |
| 01/10/2024 | COT - RSBU - Interior Shear Bracing | N/A | Re-inspection required | 1/10/24: no approved plans on site. |
| 04/22/2024 | COT - RSEL - Electrical Final | N/A | Re-inspection required | 4/22/24: Called builder at 9:25am to inform him that it would be later in the day before I could get to his site for inspection. He stated the house would be unlocked and the plans sitting on the counter. I arrived at 4:45 pm, the house is locked and none of the Project Manager's are available to take my phone call. Therefore these final inspections are going to have to be recalled for tomorrow or another day. |
| 04/22/2024 | COT - RSME - Mechanical Final | N/A | Re-inspection required | 4/22/24: Called builder at 9:25am to inform him that it would be later in the day before I could get to his site for inspection. He stated the house would be unlocked and the plans sitting on the counter. I arrived at 4:45 pm, the house is locked and none of the Project Manager's are available to take my phone call. Therefore these final inspections are going to have to be recalled for tomorrow or another day. |
| 04/22/2024 | COT - RSPL - Plumbing Final | N/A | Re-inspection required | 4/22/24: Called builder at 9:25am to inform him that it would be later in the day before I could get to his site for inspection. He stated the house would be unlocked and the plans sitting on the counter. I arrived at 4:45 pm, the house is locked and none of the Project Manager's are available to take my phone call. Therefore these final inspections are going to have to be recalled for tomorrow or another day. |
| 04/22/2024 | RSBU - Building Final | N/A | Re-inspection required | 4/22/24: Called builder at 9:25am to inform him that it would be later in the day before I could get to his site for inspection. He stated the house would be unlocked and the plans sitting on the counter. I arrived at 4:45 pm, the house is locked and none of the Project Manager's are available to take my phone call. Therefore these final inspections are going to have to be recalled for tomorrow or another day. |
| 04/22/2024 | RSBU - Building Progress | N/A | Re-inspection required | 4/22/24: Called builder at 9:25am to inform him that it would be later in the day before I could get to his site for inspection. He stated the house would be unlocked and the plans sitting on the counter. I arrived at 4:45 pm, the house is locked and none of the Project Manager's are available to take my phone call. Therefore these final inspections are going to have to be recalled for tomorrow or another day. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0523-01070
Permit Description: SFR RKF55F T21-M0087
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/02/2023 | COT - RSPL - Rough Soil | Passed | ||
| 08/02/2023 | COT - RSPL - Sewer | Passed | ||
| 08/02/2023 | COT - RSPL - Yard Water Line | Passed | ||
| 08/24/2023 | COT - RSBU - Preslab | Passed | ||
| 08/24/2023 | COT - RSEL - Electrical Underground | Passed | ||
| 08/24/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
| 10/02/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 10/02/2023 | COT - RSBU - Roof Nailing | Passed | ||
| 10/20/2023 | BULD - Electrical Clearance | Passed | ||
| 12/20/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 12/20/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
| 01/12/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 03/20/2024 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
| 04/15/2024 | ENGR Engineering Final | Passed | Contractor did not finish the riprap on the south west corner of the south wall. And the gate is not installed. | |
| 04/22/2024 | COT - RSEL - Outdoor Lighting | Passed | 4/22/24: Outdoor lights are properly installed per plans and are fully operational. | |
| 04/24/2024 | COT - RSEL - Electrical Final | Passed | 4/24/24: Construction, mechanical, electrical, and plumbing are complete. Mechanical, electrical, and plumbing fixtures are installed and operational. GFCI Receptacles are installed in bathrooms and kitchen, GFCI breaker is installed in panel for garage. Light and receptacle is installed in attic for mechanical equipment. AFCI Breakers are installed in panel for bedrooms and other outlets. Okay to issue Certificate of Occupancy for this project and permit. | |
| 04/24/2024 | COT - RSME - Mechanical Final | Passed | 4/24/24: Construction, mechanical, electrical, and plumbing are complete. Mechanical, electrical, and plumbing fixtures are installed and operational. GFCI Receptacles are installed in bathrooms and kitchen, GFCI breaker is installed in panel for garage. Light and receptacle is installed in attic for mechanical equipment. AFCI Breakers are installed in panel for bedrooms and other outlets. Okay to issue Certificate of Occupancy for this project and permit. | |
| 04/24/2024 | COT - RSPL - Plumbing Final | Passed | 4/24/24: Construction, mechanical, electrical, and plumbing are complete. Mechanical, electrical, and plumbing fixtures are installed and operational. GFCI Receptacles are installed in bathrooms and kitchen, GFCI breaker is installed in panel for garage. Light and receptacle is installed in attic for mechanical equipment. AFCI Breakers are installed in panel for bedrooms and other outlets. Okay to issue Certificate of Occupancy for this project and permit. | |
| 04/24/2024 | RSBU - Building Final | Passed | 4/24/24: Construction, mechanical, electrical, and plumbing are complete. Mechanical, electrical, and plumbing fixtures are installed and operational. GFCI Receptacles are installed in bathrooms and kitchen, GFCI breaker is installed in panel for garage. Light and receptacle is installed in attic for mechanical equipment. AFCI Breakers are installed in panel for bedrooms and other outlets. Okay to issue Certificate of Occupancy for this project and permit. | |
| 04/24/2024 | RSBU - Building Progress | Passed | 4/24/24: Construction, mechanical, electrical, and plumbing are complete. Mechanical, electrical, and plumbing fixtures are installed and operational. GFCI Receptacles are installed in bathrooms and kitchen, GFCI breaker is installed in panel for garage. Light and receptacle is installed in attic for mechanical equipment. AFCI Breakers are installed in panel for bedrooms and other outlets. Okay to issue Certificate of Occupancy for this project and permit. |