Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
08/09/2023
Applicant:
Description:
VC 1465-130

Permit Reviews

Permit Number - TC-MDP-0523-00984
Permit Status: Inspections complete
Permit Description: VC 1465-130
Start Date Submittal Complete Date Status  
08/09/2023 ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 08/21/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0523-00984
Permit Status: Inspections complete
Permit Description: VC 1465-130
Total Outstanding Activity Conditions - 6
Date Name
04/03/2023 Post-Tension Inspection Report is required.
04/03/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
08/09/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
08/09/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
08/11/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
08/18/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Conditions

Permit Number - TC-MDP-0523-00984
Permit Status: Inspections complete
Permit Description: VC 1465-130
Date Description Comments
05/09/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
08/11/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0523-00984
Permit Description: VC 1465-130
Total Completed Inspections - 22
Date Description Inspector Results Comments
09/01/2023 COT - RSPL - Rough Soil Passed
09/01/2023 COT - RSPL - Backwater Valve Passed
09/01/2023 COT - RSPL - Sewer Passed
09/01/2023 COT - RSPL - Yard Water Line Passed
09/15/2023 COT - RSBU - Excavation/Rebar/Zoning Passed 9/15/23 Side yard setback calls for 10 ft about 1 inch and a half short talked to manager Dave
09/15/2023 COT - RSBU - Preslab Passed 9/15/23 Side yard setback calls for 10 ft about 1 inch and a half short talked to manager Dave
09/15/2023 COT - RSEL - Electrical Underground Passed 9/15/23 Side yard setback calls for 10 ft about 1 inch and a half short talked to manager Dave
09/15/2023 COT - RSEL - Grounding/Bonding Passed 9/15/23 Side yard setback calls for 10 ft about 1 inch and a half short talked to manager Dave
09/29/2023 COT - RSBU - Exterior Clips/Sheathing Passed
09/29/2023 COT - RSBU - Roof Nailing Passed
10/19/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
10/19/2023 COT - RSPL - Gas Pressure Test Passed
10/20/2023 RSBU - Building Progress Passed
10/20/2023 BULD - Electrical Clearance Passed Clearance for TEP ECO. 10/20/2023
10/26/2023 COT - RSBU - Interior Shear Bracing Passed
12/13/2023 COT - BULD - SWG Clearance Passed
01/09/2024 COT - RSEL - Electrical Final Passed
01/09/2024 COT - RSEL - Outdoor Lighting Passed
01/09/2024 COT - RSME - Mechanical Final Passed
01/09/2024 ENGR Engineering Final Passed
01/19/2024 COT - RSPL - Plumbing Final Passed
01/19/2024 RSBU - Building Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
VALENCIA CROSSING - LOT 23 START_V1.PDF DOCUMENTS VIEW
VC 23 SIC-2023-08-09_V1.PDF DOCUMENTS VIEW