Permit Details

Status:
Inspections
Type:
Model Building Permit
Address NEW:
1216 E LIGGINS ST
Apply Date:
04/29/2026
Applicant:
Mark Alteri
Description:
REV1: house moved from one side of the lot to the other side of the lot PV 2378SFR (Model master plan TC-MDP-0124-00026) REV 4

Permit Reviews

Permit Number - TC-MDP-0426-00257
Permit Status: Inspections
Permit Description: REV1: house moved from one side of the lot to the other side of the lot PV 2378SFR (Model master plan TC-MDP-0124-00026) REV 4
Start Date Submittal Complete Date Status  
09/18/2026 SPECIAL INSPECTION REVIEW v.1 09/18/2026 APPROVED Review Details
07/14/2026 SITE FROM MODEL PERMIT - SUBDIVISION REVISION v.1 07/17/2026 APPROVED Review Details
05/04/2026 SITE FROM MODEL PERMIT - SUBDIVISION v.1 05/11/2026 APPROVED Review Details
09/08/2026 SPECIAL INSPECTION REVIEW v.1 09/08/2026 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0426-00257
Permit Status: Inspections
Permit Description: REV1: house moved from one side of the lot to the other side of the lot PV 2378SFR (Model master plan TC-MDP-0124-00026) REV 4
Date Description Comments
09/08/2026 Prior to Final - Special Inspections - SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/23/2026 Post-Tension Inspection Report is required.
04/23/2026 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
04/23/2026 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-MDP-0426-00257
Permite Description: REV1: house moved from one side of the lot to the other side of the lot PV 2378SFR (Model master plan TC-MDP-0124-00026) REV 4
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
08/10/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Re-inspection required Missing anchor bolt and over penetrated nailing east wall
08/10/2026 COT - RSBU - Roof Nailing N/A Re-inspection required Missing anchor bolt and over penetrated nailing east wall
09/08/2026 RSBU - Building Progress N/A Partial Pass 9-8-26: exterior firewall approved. Okay to continue with construction at progress areas.

Completed Inspections

Permit Status: Inspections
Permit Number: TC-MDP-0426-00257
Permit Description: REV1: house moved from one side of the lot to the other side of the lot PV 2378SFR (Model master plan TC-MDP-0124-00026) REV 4
Total Completed Inspections - 9
Date Description Inspector Results Comments
06/23/2026 COT - RSPL - Yard Water Line Passed 06/23/2026
Holding under test. Okay to backfill, shading required.
06/23/2026 COT - RSPL - Sewer Passed 06/23/2026
Holding under test to HCS. Okay to backfill, shading required.
06/23/2026 COT - RSPL - Rough Soil Passed 06/23/2026
Holding under test. Okay to backfill, shading required.
06/30/2026 COT - RSBU - Preslab Passed 06/30/2026
Approved per plan and reinforcement. Okay for concrete placement.
06/30/2026 COT - RSBU - Excavation/Rebar/Zoning Passed
06/30/2026 COT - RSEL - Electrical Underground Passed
08/11/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Corrections were made. 8/11/2026
08/11/2026 COT - RSBU - Roof Nailing Passed Corrections were made. 8/11/2026
08/19/2026 BULD - Electrical Clearance Passed TEP CLEARANCE: ECO