Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
04/10/2026
Applicant:
Celina Rodriguez
Description:
Mirador Ridge Blossom 1465 Plan (Model master plan TC-MDP-0725-00408)

Permit Reviews

Permit Number - TC-MDP-0426-00221
Permit Status: Inspections complete
Permit Description: Mirador Ridge Blossom 1465 Plan (Model master plan TC-MDP-0725-00408)
Start Date Submittal Complete Date Status  
08/28/2026 SPECIAL INSPECTION REVIEW v.1 09/01/2026 APPROVED Review Details
04/15/2026 SITE FROM MODEL PERMIT - SUBDIVISION v.1 04/24/2026 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0426-00221
Permit Status: Inspections complete
Permit Description: Mirador Ridge Blossom 1465 Plan (Model master plan TC-MDP-0725-00408)
Date Description Comments
04/09/2026 Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections.
04/22/2026 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/24/2026 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
04/09/2026 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
04/22/2026 Post-Installed Anchor Inspection Report is required.
04/09/2026 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
04/22/2026 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
04/09/2026 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0426-00221
Permite Description: Mirador Ridge Blossom 1465 Plan (Model master plan TC-MDP-0725-00408)
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
08/19/2026 COT - RSME - Mechanical Final N/A Re-inspection required 8-19-26 missing caps at condensing unit
08/19/2026 RSBU - Building Final N/A Partial Pass 8-19-26 Building final approved, pending conditions to be satisfied
08/18/2026 ENGR Engineering Final N/A Partial Pass Site is complete in accordance with approved plans.
Outstanding conditions are pending approval.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0426-00221
Permit Description: Mirador Ridge Blossom 1465 Plan (Model master plan TC-MDP-0725-00408)
Total Completed Inspections - 20
Date Description Inspector Results Comments
04/29/2026 COT - RSPL - Rough Soil Passed 04/29/2026
All fixtures holding under test - okay to backfill, shading required.
04/29/2026 COT - RSPL - Yard Water Line Passed 04/29/2026
Holding under test to meter - okay to backfill, shading required.
05/04/2026 COT - RSBU - Preslab Passed 05/04/2026
Approved per plan and reinforcement. Okay for concrete placement.
05/04/2026 COT - RSBU - Excavation/Rebar/Zoning Passed 05/04/2026
Approved per plan and reinforcement. Okay for concrete placement.
05/04/2026 COT - RSEL - Electrical Underground Passed
05/18/2026 COT - RSBU - Roof Nailing Passed
05/20/2026 COT - RSPL - Sewer Passed 5.20.26
Approved
05/20/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 5.20.26
Approved
06/03/2026 COT - RSPL - Gas Pressure Test Passed
06/04/2026 BULD - Electrical Clearance Passed
06/04/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
06/23/2026 COT - RSBU - Interior Shear Bracing Passed
07/29/2026 COT - BULD - SWG Clearance Passed Clearance for Southwest Gas. 7/29/2026
08/19/2026 COT - RSEL - Outdoor Lighting Passed
08/19/2026 COT - RSPL - Plumbing Final Passed 8-19-26 plumbing final approved
08/19/2026 RSBU - Building Progress Passed
08/19/2026 COT - RSEL - Electrical Final Passed 8-19-26. Electrical final approved
08/20/2026 COT - RSME - Mechanical Final Passed 8-20-26 all corrections have been made
09/11/2026 RSBU - Building Final Passed
09/11/2026 ENGR Engineering Final Passed

Documents

File Name Document Type  
PT PACKET- MRB 65-2026-08-26_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
MIRADOR RIDGE - LOT 65 START 2_V1.PDF DOCUMENTS VIEW
MR BLOSSOM 65 SIC-2026-04-10_V1.PDF DOCUMENTS VIEW