Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Address NEW:
2711 S OAKENSHIELD WY
Apply Date:
04/29/2025
Applicant:
Chris Irby
Description:
1453T Ireland We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)

Permit Reviews

Permit Number - TC-MDP-0425-00268
Permit Status: Complete
Permit Description: 1453T Ireland We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)
Start Date Submittal Complete Date Status  
05/05/2025 SITE FROM MODEL PERMIT - SUBDIVISION v.1 05/13/2025 APPROVED Review Details
12/08/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/10/2025 REQUIRES RESUBMIT Review Details
01/07/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.2 01/09/2026 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0425-00268
Permit Status: Complete
Permit Description: 1453T Ireland We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)
Date Description Comments
05/05/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
04/29/2025 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/29/2025 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
04/29/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
04/29/2025 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/
05/07/2025 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0425-00268
Permite Description: 1453T Ireland We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
06/23/2025 COT - RSEL - Electrical Underground N/A Not Applicable site does not run underground electric

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0425-00268
Permit Description: 1453T Ireland We have purchased this plan/property from Cornerstone Homes and would like to permit from previously approved plan. (Model master plan TC-MDP-0125-00009)
Total Completed Inspections - 20
Date Description Inspector Results Comments
06/18/2025 BULD - Electrical Clearance Passed Ready for temp power CLEARANCE ECO
06/18/2025 COT - RSPL - Rough Soil Passed Passed 6/18/25 ok to backfill
06/18/2025 COT - RSPL - Sewer Passed Passed 6/18/25 ok to backfill
06/18/2025 COT - RSPL - Yard Water Line Passed Passed 6/18/25 ok to backfill
06/23/2025 COT - RSBU - Excavation/Rebar/Zoning Passed Passed 6/23/25 ok to pour concrete
06/23/2025 COT - RSBU - Preslab Passed Passed 6/23/25 ok to pour concrete
07/02/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Passed 7/2/25
07/02/2025 COT - RSBU - Roof Nailing Passed Passed 7/2/25
07/21/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Passed 7/21/25
07/21/2025 COT - RSEL - Grounding/Bonding Passed Passed 7/21/25
08/07/2025 COT - RSBU - Interior Shear Bracing Passed Passed 8/7/25
09/10/2025 COT - BULD - SWG Clearance Passed Passed 9/10/25 CLEARANCE SWG
09/10/2025 COT - RSEL - Electrical Final Passed Passed 9/10/25
09/10/2025 COT - RSEL - Outdoor Lighting Passed Passed 9/10/25
09/10/2025 COT - RSME - Mechanical Final Passed Passed 9/10/25
09/10/2025 COT - RSPL - Gas Pressure Test Passed Passed 9/10/25
09/10/2025 COT - RSPL - Plumbing Final Passed Passed 9/10/25
09/10/2025 RSBU - Building Final Passed Passed 9/10/25
09/10/2025 RSBU - Building Progress Passed Passed 9/10/25
09/24/2025 ENGR Engineering Final Passed Site is clean and accessible, in accordance with plans.

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL (SSRS).PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
RIVENDELL LOT 32-START REVISED_V1.PDF DOCUMENTS VIEW
RIVENDELL SPECIAL INSPECTION CERT-LOT 32 2711 S OAKENSHIELD WAY-2025-04-29_V1.PDF DOCUMENTS VIEW