Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Model Building Permit
Address NEW:
9834 E GRAY HAWK DR
Apply Date:
03/14/2025
Applicant:
Helen Ormsby
Description:
Casas del Cerrito H35G Model Plan (Model master plan TC-MDP-0823-01442)

Permit Reviews

Permit Number - TC-MDP-0425-00221
Permit Status: Issued
Permit Description: Casas del Cerrito H35G Model Plan (Model master plan TC-MDP-0823-01442)
Start Date Submittal Complete Date Status  
09/26/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 09/29/2025 APPROVED Review Details
04/04/2025 SITE FROM MODEL PERMIT - PRODUCTION v.1 04/14/2025 APPROVED Review Details
07/02/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/02/2025 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0425-00221
Permit Status: Issued
Permit Description: Casas del Cerrito H35G Model Plan (Model master plan TC-MDP-0823-01442)
Total Outstanding Activity Conditions - 1
Date Name
04/01/2025 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/

Conditions

Permit Number - TC-MDP-0425-00221
Permit Status: Issued
Permit Description: Casas del Cerrito H35G Model Plan (Model master plan TC-MDP-0823-01442)
Date Description Comments
04/04/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
04/01/2025 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
04/13/2025 Post-Installed Anchor Inspection Report is required.
04/13/2025 Post-Tension Inspection Report is required.
04/01/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
04/13/2025 Soil Compaction Special Inspection is Required.
04/13/2025 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-MDP-0425-00221
Permite Description: Casas del Cerrito H35G Model Plan (Model master plan TC-MDP-0823-01442)
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
06/30/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Re-inspection required 6/30/25 issues still remain
06/06/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Partial Pass 6/6/25
Partial pass:Provide blocking for future grab bars for toilets. 33"-36" above floor to allow for a 42" grab bar.

Completed Inspections

Permit Status: Issued
Permit Number: TC-MDP-0425-00221
Permit Description: Casas del Cerrito H35G Model Plan (Model master plan TC-MDP-0823-01442)
Total Completed Inspections - 22
Date Description Inspector Results Comments
05/16/2025 COT - RSPL - Backwater Valve Passed Passed 5/16/25 ok to backfill
05/16/2025 COT - RSPL - Rough Soil Passed Passed 5/16/25 ok to backfill
05/16/2025 COT - RSPL - Sewer Passed Passed 5/16/25 ok to backfill
05/16/2025 COT - RSPL - Yard Water Line Passed Passed 5/16/25 ok to backfill
05/23/2025 COT - RSEL - Grounding/Bonding Passed Passed 5/23/25 ok to pour concrete
05/23/2025 BULD - Electrical Clearance Passed Passed 5/23/25 CLEARANCE ECO
05/23/2025 COT - RSBU - Excavation/Rebar/Zoning Passed Passed 5/23/25 ok to pour concrete
05/23/2025 COT - RSBU - Preslab Passed Passed 5/23/25 ok to pour concrete
05/23/2025 COT - RSEL - Electrical Underground Passed Passed 5/23/25 ok to pour concrete
06/06/2025 COT - RSBU - Roof Nailing Passed
06/25/2025 COT - RSPL - Gas Pressure Test Passed Passed 6/25/25
06/30/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 6/30/25 corrections made
07/21/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 7/21/25 corrections made at intermediate
07/21/2025 COT - RSBU - Interior Shear Bracing Passed Passed 7/21/25
09/05/2025 COT - BULD - SWG Clearance Passed SOUTHWEST GAS CLEARANCE: SWG
09/16/2025 COT - RSME - Mechanical Final Passed Passed final 9/16/25
09/16/2025 ENGR Engineering Final Passed Site is clean and accessible, complete in accordance with approved plans.
09/16/2025 COT - RSEL - Outdoor Lighting Passed Passed final 9/16/25
09/16/2025 COT - RSPL - Plumbing Final Passed Passed final 9/16/25
09/16/2025 RSBU - Building Progress Passed passed 9/16/25
09/16/2025 COT - RSEL - Electrical Final Passed Passed final 9/16/25
09/19/2025 RSBU - Building Final Passed

Documents

File Name Document Type  
CDC 27 SIC-2025-07-01_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CDC 27 D1_V1.PDF DOCUMENTS VIEW
CDC 27 SIC-2025-04-03_V1.PDF DOCUMENTS VIEW