Permit: TC-MDP-0424-00508
Permit Details
Apply Date:
05/30/2024
Applicant:
Dana Petty
Description:
SFR 230.2380 T21-M0028
Permit Reviews
Permit Number - TC-MDP-0424-00508
Permit Status: Complete
Permit Description: SFR 230.2380 T21-M0028
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/18/2024 | APPROVED |
01/15/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/15/2025 | APPROVED |
05/31/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 06/04/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0424-00508
Permit Status: Complete
Permit Description: SFR 230.2380 T21-M0028
Date | Description | Comments |
---|---|---|
06/03/2024 | Post-Installed Anchor Inspection Report is required. | |
06/03/2024 | Post-Tension Inspection Report is required. | |
04/25/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/25/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
06/03/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0424-00508
Permite Description: SFR 230.2380 T21-M0028
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/16/2024 | COT - RSBU - Interior Shear Bracing | N/A | Not Ready | Not ready, workers still hanging drywall |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0424-00508
Permit Description: SFR 230.2380 T21-M0028
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/31/2024 | COT - RSPL - Sewer | Passed | ||
07/31/2024 | COT - RSPL - Yard Water Line | Passed | ||
08/01/2024 | COT - RSPL - Rough Soil | Passed | 8/1/2024 okay to backfill. Shading required. | |
08/07/2024 | COT - RSEL - Electrical Underground | Passed | ||
08/07/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
08/08/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
08/08/2024 | COT - RSBU - Preslab | Passed | ||
08/27/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
08/27/2024 | COT - RSBU - Roof Nailing | Passed | ||
09/26/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
09/27/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 9/27/2024 | |
09/27/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Corrections were made. 9/27/2024 | |
10/17/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
12/04/2024 | COT - BULD - SWG Clearance | Passed | 12-4-24, approved for Southwest gas connection. | |
12/06/2024 | COT - RSEL - Electrical Final | Passed | 12-6-24, electrical, outdoor lighting, plumbing, mechanical, building final approved. | |
12/06/2024 | COT - RSEL - Outdoor Lighting | Passed | 12-6-24, electrical, outdoor lighting, plumbing, mechanical, building final approved. | |
12/06/2024 | COT - RSME - Mechanical Final | Passed | 12-6-24, electrical, outdoor lighting, plumbing, mechanical, building final approved. | |
12/06/2024 | COT - RSPL - Plumbing Final | Passed | 12-6-24, electrical, outdoor lighting, plumbing, mechanical, building final approved. | |
12/06/2024 | ENGR Engineering Final | Passed | CO Ready Low voltage riser is damaged |
|
12/06/2024 | RSBU - Building Final | Passed | 12-6-24, electrical, outdoor lighting, plumbing, mechanical, building final approved. | |
12/06/2024 | RSBU - Building Progress | Passed | 12-6-24, electrical, outdoor lighting, plumbing, mechanical, building final approved. |