Permit: TC-MDP-0424-00502
Permit Details
Apply Date:
04/19/2024
Applicant:
Celina Rodriguez
Description:
SFR BT2013-140 T22-M0036
Permit Reviews
Permit Number - TC-MDP-0424-00502
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/19/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 05/01/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0424-00502
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
04/17/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
04/19/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
04/19/2024 | Post-Installed Anchor Inspection Report is required. |
04/19/2024 | Post-Tension Inspection Report is required. |
04/19/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0424-00502
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Date | Description | Comments |
---|---|---|
04/17/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0424-00502
Permite Description: SFR BT2013-140 T22-M0036
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/31/2024 | COT - RSEL - Electrical Final | N/A | Re-inspection required | 10-31-24, 2 missing knockouts at main panel, thermostats must be installed at a maximum height of 54 inches (per approved plans), and provide ladder for attic access. |
10/31/2024 | COT - RSEL - Outdoor Lighting | N/A | Re-inspection required | 10-31-24, 2 missing knockouts at main panel, thermostats must be installed at a maximum height of 54 inches (per approved plans), and provide ladder for attic access. |
10/31/2024 | COT - RSME - Mechanical Final | N/A | Re-inspection required | 10-31-24, 2 missing knockouts at main panel, thermostats must be installed at a maximum height of 54 inches (per approved plans), and provide ladder for attic access. |
10/31/2024 | COT - RSPL - Plumbing Final | N/A | Re-inspection required | 10-31-24, 2 missing knockouts at main panel, thermostats must be installed at a maximum height of 54 inches (per approved plans), and provide ladder for attic access. |
10/31/2024 | RSBU - Building Final | N/A | Re-inspection required | 10-31-24, 2 missing knockouts at main panel, thermostats must be installed at a maximum height of 54 inches (per approved plans), and provide ladder for attic access. |
10/31/2024 | RSBU - Building Progress | N/A | Re-inspection required | 10-31-24, 2 missing knockouts at main panel, thermostats must be installed at a maximum height of 54 inches (per approved plans), and provide ladder for attic access. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0424-00502
Permit Description: SFR BT2013-140 T22-M0036
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/31/2024 | COT - RSPL - Yard Water Line | Passed | ||
05/31/2024 | COT - RSPL - Sewer | Passed | ||
05/31/2024 | COT - RSPL - Rough Soil | Passed | ||
06/07/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
06/07/2024 | COT - RSBU - Preslab | Passed | ||
06/07/2024 | COT - RSEL - Electrical Underground | Passed | ||
06/07/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
06/28/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | Exterior walls are properly secured to concrete floors with j-bolts, titan bolts, or shot pins. Plywood sheathing is properly nailed per plan and code requirements. Shear wall hold downs are properly nailed and bolted to concrete floor. Okay to proceed with mechanical, electrical, and plumbing rough-in. | |
06/28/2024 | COT - RSBU - Roof Nailing | Passed | Roof trusses are properly secured to top plate with nails and H2.5 CLIPS. Sheathing is properly installed and nailed down per plan and code requirements. Okay to proceed with mechanical, electrical, and plumbing rough-in. | |
08/06/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
08/06/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
08/13/2024 | BULD - Electrical Clearance | Passed | ||
08/21/2024 | COT - RSBU - Interior Shear Bracing | Passed | Drywall for interior shear braced walls is properly secured to studs with drywall screws at the spacing called for on the plans. Okay to tape, texture, and paint all walls and ceilings. | |
10/16/2024 | COT - BULD - SWG Clearance | Passed | Gas equipment and valves are installed. SWG Clearance issued to Southwest Gas Company to install meter and turn on gas. | |
10/31/2024 | ENGR Engineering Final | Passed | ||
11/07/2024 | COT - RSEL - Electrical Final | Passed | ||
11/07/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
11/07/2024 | COT - RSME - Mechanical Final | Passed | ||
11/07/2024 | COT - RSPL - Plumbing Final | Passed | ||
11/07/2024 | RSBU - Building Final | Passed | ||
11/07/2024 | RSBU - Building Progress | Passed |