Permit: TC-MDP-0424-00483
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
9774 E GRAY HAWK DR
Address NEW:
9774 E GRAY HAWK DR
Apply Date:
04/17/2024
Applicant:
Helen Ormsby
Description:
Casas del Cerrito H35G Model Plan
Permit Reviews
Permit Number - TC-MDP-0424-00483
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35G Model Plan
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/16/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/17/2024 | APPROVED |
| 04/18/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 04/24/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0424-00483
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35G Model Plan
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 04/17/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
| 04/19/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 04/19/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0424-00483
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35G Model Plan
| Date | Description | Comments |
|---|---|---|
| 04/19/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 04/17/2024 | Post-Tension Inspection Report is required. | |
| 04/17/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 04/19/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0424-00483
Permite Description: Casas del Cerrito H35G Model Plan
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/22/2024 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Re-inspection required | 5/22/24: rebar not to schedule at front of house . |
| 05/22/2024 | COT - RSBU - Preslab | N/A | Re-inspection required | 5/22/24: rebar not to schedule at front of house . |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0424-00483
Permit Description: Casas del Cerrito H35G Model Plan
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/09/2024 | COT - RSPL - Backwater Valve | Passed | ||
| 05/09/2024 | COT - RSPL - Rough Soil | Passed | ||
| 05/09/2024 | COT - RSPL - Sewer | Passed | ||
| 05/09/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 05/22/2024 | BULD - Electrical Clearance | Passed | TEP eco | |
| 05/22/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 05/22/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 05/23/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 05/23/2024 | COT - RSBU - Preslab | Passed | ||
| 06/13/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 06/13/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 06/25/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
| 06/27/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 07/08/2024 | COT - RSBU - Interior Shear Bracing | Passed | Drywall on interior shear walls is properly installed and secured to studs with the proper screw placement per the plan. | |
| 08/27/2024 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
| 09/05/2024 | COT - RSEL - Electrical Final | Passed | Construction is complete. Okay to issue Certificate of Occupancy. | |
| 09/05/2024 | COT - RSEL - Outdoor Lighting | Passed | Construction is complete. Okay to issue Certificate of Occupancy. | |
| 09/05/2024 | COT - RSME - Mechanical Final | Passed | Construction is complete. Okay to issue Certificate of Occupancy. | |
| 09/05/2024 | COT - RSPL - Plumbing Final | Passed | Construction is complete. Okay to issue Certificate of Occupancy. | |
| 09/05/2024 | RSBU - Building Final | Passed | Construction is complete. Okay to issue Certificate of Occupancy. | |
| 09/05/2024 | RSBU - Building Progress | Passed | Construction is complete. Okay to issue Certificate of Occupancy. | |
| 09/13/2024 | ENGR Engineering Final | Passed | Move in ready |