Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Address NEW:
9787 E GRAY HAWK DR
Apply Date:
04/19/2024
Applicant:
Helen Ormsby
Description:
Casas del Cerrito H35D Model Plan

Permit Reviews

Permit Number - TC-MDP-0424-00453
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35D Model Plan
Start Date Submittal Complete Date Status  
04/19/2024 SITE FROM MODEL PERMIT - SUBDIVISION v.1 05/02/2024 APPROVED Review Details
09/16/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/17/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0424-00453
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35D Model Plan
Total Outstanding Activity Conditions - 1
Date Name
04/17/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.

Conditions

Permit Number - TC-MDP-0424-00453
Permit Status: Inspections complete
Permit Description: Casas del Cerrito H35D Model Plan
Date Description Comments
04/19/2024 Post-Installed Anchor Inspection Report is required.
04/17/2024 Post-Tension Inspection Report is required.
04/17/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
04/19/2024 Soils Testing special inspection report is required.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0424-00453
Permite Description: Casas del Cerrito H35D Model Plan
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
10/10/2024 RSBU - Building Progress N/A Not Applicable
09/26/2024 ENGR Engineering Final N/A Not Ready Cleanouts need to be cut down and capped, missing breakers, etc.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0424-00453
Permit Description: Casas del Cerrito H35D Model Plan
Total Completed Inspections - 20
Date Description Inspector Results Comments
06/21/2024 COT - RSPL - Rough Soil Passed
06/21/2024 COT - RSPL - Sewer Passed
06/21/2024 COT - RSPL - Yard Water Line Passed
06/27/2024 COT - RSBU - Preslab Passed
06/27/2024 COT - RSEL - Electrical Underground Passed
07/15/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
07/16/2024 COT - RSBU - Roof Nailing Passed
07/17/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 7/17/24: studs are in for girder will check for anchor bolts at intermediate
08/01/2024 COT - RSPL - Gas Pressure Test Passed
08/01/2024 BULD - Electrical Clearance Passed Clearance for TEP ECO. 8/1/2024
08/02/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 8/2/24: Gas line elbows and T's have been properly supported with blocking, refrigerator is on a dedicated circuit, and water lines have been pressurized to 60 psi with no leaks. Okay to proceed with installation of insulation and drywall.
08/16/2024 COT - RSBU - Interior Shear Bracing Passed Drywall is properly installed on interior shear walls per plan requirements. Okay to proceed with tape, texture, and painting of walls and ceilings.
10/04/2024 COT - BULD - SWG Clearance Passed 10/4/24: SWG clearance for meter tag
10/14/2024 ENGR Engineering Final Passed CO Ready
11/06/2024 COT - RSEL - Electrical Final Passed
11/06/2024 COT - RSEL - Grounding/Bonding Passed
11/06/2024 COT - RSEL - Outdoor Lighting Passed
11/06/2024 COT - RSME - Mechanical Final Passed
11/06/2024 COT - RSPL - Plumbing Final Passed
11/06/2024 RSBU - Building Final Passed

Documents

File Name Document Type  
CDC 12 SIC-2024-09-13_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CDC 12 SIC-2024-04-19_V1.PDF DOCUMENTS VIEW
CONS-CDC 12 D1_V1.PDF DOCUMENTS VIEW