Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0424-00451
Permit Details
Apply Date:
04/22/2024
Applicant:
Joshua Swinney
Description:
Great Sand Dunes SFR Model Escalara
Permit Reviews
Permit Number - TC-MDP-0424-00451
Permit Status: Issued
Permit Description: Great Sand Dunes SFR Model Escalara
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/26/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 05/01/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0424-00451
Permit Status: Issued
Permit Description: Great Sand Dunes SFR Model Escalara
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
04/17/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
04/26/2024 | Post-Installed Anchor Inspection Report is required. |
04/26/2024 | Post-Tension Inspection Report is required. |
04/26/2024 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0424-00451
Permit Status: Issued
Permit Description: Great Sand Dunes SFR Model Escalara
Date | Description | Comments |
---|---|---|
05/01/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
04/17/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/26/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-MDP-0424-00451
Permite Description: Great Sand Dunes SFR Model Escalara
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/06/2024 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable | |
09/06/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Issued
Permit Number: TC-MDP-0424-00451
Permit Description: Great Sand Dunes SFR Model Escalara
Total Completed Inspections - 11
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/30/2024 | COT - RSPL - Rough Soil | Passed | ||
05/30/2024 | COT - RSPL - Yard Water Line | Passed | ||
06/11/2024 | COT - RSEL - Electrical Underground | Passed | ||
06/11/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
06/12/2024 | COT - RSBU - Preslab | Passed | 6/12/24: Missing shear wall hold down has been installed next to bathroom. Concrete forms are set, post tension cabling is properly installed and evenly spaced, rebar reinforcement is in place per plans, masa clips and shear wall hold downs are properly secured to form, subsoil is compacted, underground plumbing is properly wrapped with foam, underground electrical is installed for kitchen island, and Ufer ground is installed in footing on garage side of house. | |
06/12/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 6/12/24: Missing shear wall hold down has been installed next to bathroom. Concrete forms are set, post tension cabling is properly installed and evenly spaced, rebar reinforcement is in place per plans, masa clips and shear wall hold downs are properly secured to form, subsoil is compacted, underground plumbing is properly wrapped with foam, underground electrical is installed for kitchen island, and Ufer ground is installed in footing on garage side of house. | |
07/15/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
07/15/2024 | COT - RSBU - Roof Nailing | Passed | ||
09/18/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
09/19/2024 | COT - RSPL - Sewer | Passed | ||
10/04/2024 | COT - RSBU - Interior Shear Bracing | Passed | Passed interior shear bracing 10/04/24 |