Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0424-00434
Permit Details
Apply Date:
04/12/2024
Applicant:
Daria Hopkins
Description:
SFR MER1402190 T21-M0078
Permit Reviews
Permit Number - TC-MDP-0424-00434
Permit Status: Issued
Permit Description: SFR MER1402190 T21-M0078
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/15/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 04/22/2024 | APPROVED |
10/03/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/04/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0424-00434
Permit Status: Issued
Permit Description: SFR MER1402190 T21-M0078
Date | Description | Comments |
---|---|---|
04/18/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
04/18/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
04/18/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
04/18/2024 | Post-Tension Inspection Report is required. | |
04/12/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/12/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
04/18/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-MDP-0424-00434
Permite Description: SFR MER1402190 T21-M0078
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/17/2024 | COT - RSBU - Interior Shear Bracing | N/A | Re-inspection required | 10-17-24, shear walls and ceiling throughout not per schedule. |
12/13/2024 | ENGR Engineering Final | N/A | Re-inspection required | No house numbers. Drainage slope on both sides of house unclear, seems mostly level with grout lines. West wall, some caps not grouted in place. Some construction debris in back yard. Steel wire coming out of ground at clean out in front. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-MDP-0424-00434
Permit Description: SFR MER1402190 T21-M0078
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/15/2024 | COT - RSPL - Sewer | Passed | ||
08/15/2024 | COT - RSPL - Rough Soil | Passed | ||
08/15/2024 | COT - RSPL - Yard Water Line | Passed | ||
08/22/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
08/22/2024 | COT - RSBU - Preslab | Passed | ||
08/22/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
08/22/2024 | COT - RSEL - Electrical Underground | Passed | ||
09/06/2024 | COT - RSBU - Roof Nailing | Passed | Roof sheathing is properly secured to trusses, trusses are secured to top plate with H2.5 clips. Okay to proceed with rough-in of mechanical, electrical, and plumbing. | |
09/06/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | Exterior walls and interior walls are properly secured to concrete floor with masa clips, j-bolts, titan bolts, cut nails, or shot pins. Plywood sheathing is properly secured to studs per plan for shear walls. All masa clips and shear wall hold downs are nailed properly. Okay to proceed with rough-in. | |
09/26/2024 | BULD - Electrical Clearance | Passed | PASSED ELECTRICAL CLEARANCE ECO 9/26/24 | |
09/30/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Mechanical, electrical, and plumbing rough-in is complete. Okay to proceed with installation of insulation and drywall. | |
09/30/2024 | COT - RSPL - Gas Pressure Test | Passed | Gas lines are properly installed and under 15 psi air pressure test with no leaks. Okay to proceed. | |
10/18/2024 | COT - RSBU - Interior Shear Bracing | Passed | 10/18/24: Drywall is properly secured to studs for interior shear walls. Okay to proceed with tape, texture, and painting. | |
12/04/2024 | COT - BULD - SWG Clearance | Passed | Gas valves are installed at every gas appliance location. Okay to install meter. | |
12/13/2024 | COT - RSEL - Electrical Final | Passed | 12/13/24 pass | |
12/13/2024 | COT - RSEL - Outdoor Lighting | Passed | 12/13/24 pass | |
12/13/2024 | COT - RSME - Mechanical Final | Passed | 12/13/24 pass | |
12/13/2024 | COT - RSPL - Plumbing Final | Passed | 12/13/24 pass | |
12/13/2024 | RSBU - Building Final | Passed | 12/13/24 pass | |
12/13/2024 | RSBU - Building Progress | Passed | 12/13/24 pass |