Permit Details

Status:
Issued
Type:
Model Building Permit
Apply Date:
02/06/2023
Applicant:
Daria Hopkins
Description:
SFR MER1402190 T21-M0078

Permit Reviews

Permit Number - TC-MDP-0424-00432
Permit Status: Issued
Permit Description: SFR MER1402190 T21-M0078
Start Date Submittal Complete Date Status  
05/02/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 05/09/2024 APPROVED Review Details
10/08/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/08/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0424-00432
Permit Status: Issued
Permit Description: SFR MER1402190 T21-M0078
Date Description Comments
05/02/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
05/02/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
05/02/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
05/02/2024 Post-Tension Inspection Report is required.
04/12/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
04/12/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
05/02/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Completed Inspections

Permit Status: Issued
Permit Number: TC-MDP-0424-00432
Permit Description: SFR MER1402190 T21-M0078
Total Completed Inspections - 13
Date Description Inspector Results Comments
08/21/2024 COT - RSPL - Yard Water Line Passed
08/21/2024 COT - RSPL - Sewer Passed
08/21/2024 COT - RSPL - Rough Soil Passed
08/29/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
08/29/2024 COT - RSBU - Preslab Passed
08/29/2024 COT - RSEL - Electrical Underground Passed
09/24/2024 COT - RSBU - Roof Nailing Passed 9/24/24 Corrections made
09/25/2024 COT - RSBU - Exterior Clips/Sheathing Passed 9/25/24: Corrections have been made. Okay to proceed with rough-in.
10/18/2024 COT - RSPL - Gas Pressure Test Passed Gas line is under 15# psi with no leaks. Okay to proceed.
10/18/2024 COT - RSEL - Grounding/Bonding Passed
10/18/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Rough-in is complete. Okay to proceed with insulation and drywall installation.
10/18/2024 RSBU - Building Progress Passed
11/01/2024 COT - RSBU - Interior Shear Bracing Passed

Documents

File Name Document Type  
149880 PT LOT 50 COMPLETE-2024-10-08_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
LOT 50 PLOT PLAN_V1.PDF DOCUMENTS VIEW
LOT 50 SPECIAL INSPECTION CERTIFICATE-2024-05-02_V1.PDF DOCUMENTS VIEW