Permit: TC-MDP-0424-00431
Permit Details
Apply Date:
04/12/2024
Applicant:
Daria Hopkins
Description:
SFR MER1402190 T21-M0078
Permit Reviews
Permit Number - TC-MDP-0424-00431
Permit Status: Issued
Permit Description: SFR MER1402190 T21-M0078
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/24/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 05/28/2024 | APPROVED |
09/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/18/2024 | APPROVED |
04/15/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 04/22/2024 | APPROVED |
07/19/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 07/31/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0424-00431
Permit Status: Issued
Permit Description: SFR MER1402190 T21-M0078
Date | Description | Comments |
---|---|---|
04/18/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
04/18/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
04/18/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
04/18/2024 | Post-Tension Inspection Report is required. | |
04/12/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/12/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
09/18/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
04/18/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-MDP-0424-00431
Permite Description: SFR MER1402190 T21-M0078
Total Outstanding Inspections - 9
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/10/2024 | COT - RSBU - Interior Shear Bracing | N/A | Not Ready | 10/10/24 Intermediate inspection needs to be closed out before shear wall inspection. |
09/27/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required | |
11/25/2024 | COT - BULD - SWG Clearance | N/A | Re-inspection required | Install vent cap on water heater |
12/19/2024 | COT - RSEL - Electrical Final | N/A | Re-inspection required | 12-19-24, no access, property locked. |
12/19/2024 | COT - RSEL - Outdoor Lighting | N/A | Re-inspection required | 12-19-24, no access, property locked. |
12/19/2024 | COT - RSME - Mechanical Final | N/A | Re-inspection required | 12-19-24, no access, property locked. |
12/19/2024 | COT - RSPL - Plumbing Final | N/A | Re-inspection required | 12-19-24, no access, property locked. |
12/19/2024 | RSBU - Building Final | N/A | Re-inspection required | 12-19-24, no access. Property locked. |
12/19/2024 | RSBU - Building Progress | N/A | Re-inspection required | 12-19-24, no access, property locked. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-MDP-0424-00431
Permit Description: SFR MER1402190 T21-M0078
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/25/2024 | COT - RSPL - Yard Water Line | Passed | ||
07/25/2024 | COT - RSPL - Sewer | Passed | ||
07/25/2024 | COT - RSPL - Rough Soil | Passed | ||
08/06/2024 | COT - RSBU - Preslab | Passed | ||
08/06/2024 | COT - RSEL - Electrical Underground | Passed | ||
08/06/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
08/06/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
08/26/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
08/26/2024 | COT - RSBU - Roof Nailing | Passed | ||
09/27/2024 | BULD - Electrical Clearance | Passed | ||
09/27/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
10/11/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 10/11/24: DWV has passed. Mechanical, electrical, and plumbing rough in is complete okay to proceed. | |
11/27/2024 | COT - BULD - SWG Clearance | Passed | Gas valves are installed on all gas pipes for gas appliance locations. SWG Clearance issued. | |
12/13/2024 | ENGR Engineering Final | Passed | Construction Materials are getting cleaned up now. Missing yard gate will be installed and finished well before closing. Otherwise passes. |
Scheduled Inspections
Scheduled Inspections - TC-MDP-0424-00431
Status: Issued
Description: SFR MER1402190 T21-M0078
Scheduled Date | Description | Entered By | Entered Date |
---|---|---|---|
12/23/2024 | COT - RSEL - Electrical Final | Scheduled | |
12/23/2024 | RSBU - Building Progress | Scheduled | |
12/23/2024 | COT - RSEL - Outdoor Lighting | Scheduled | |
12/23/2024 | COT - RSPL - Plumbing Final | Scheduled | |
12/23/2024 | COT - RSME - Mechanical Final | Scheduled | |
12/23/2024 | RSBU - Building Final | Scheduled |