Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0424-00390
Permit Details
Status:
Issued
Type:
Model Building Permit
Address:
6049 E CAMPOLINA TR
Address NEW:
6049 E CAMPOLINA TR
Apply Date:
04/03/2024
Applicant:
Brian Jones
Description:
Blackhawk T934 - Frasier
Permit Reviews
Permit Number - TC-MDP-0424-00390
Permit Status: Issued
Permit Description: Blackhawk T934 - Frasier
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/04/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 04/09/2024 | APPROVED |
| 04/18/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/21/2025 | APPROVED |
| 08/04/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 08/05/2025 | APPROVED |
| 05/30/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/30/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-MDP-0424-00390
Permit Status: Issued
Permit Description: Blackhawk T934 - Frasier
| Date | Description | Comments |
|---|---|---|
| 04/08/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 04/09/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 04/08/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 04/08/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 04/01/2024 | Post-Tension Inspection Report is required. | |
| 04/01/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 04/01/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
| 04/08/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-MDP-0424-00390
Permit Description: Blackhawk T934 - Frasier
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/18/2024 | COT - RSPL - Sewer | Passed | Okay to backfill. Shading is required. 6/18/2024 | |
| 06/18/2024 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading is required. 6/18/2024 | |
| 06/18/2024 | COT - RSPL - Yard Water Line | Passed | Partial pass. Pending point of connection to meter. 6/18/2024 | |
| 06/25/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 06/25/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 06/25/2024 | COT - RSBU - Preslab | Passed | ||
| 06/25/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 07/16/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 07/16/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 08/23/2024 | BULD - Electrical Clearance | Passed | 8/23/24: TEP ECO CLEARANCE FOR 6049 E CAMPOLINA TR | |
| 08/23/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 08/23/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
| 09/10/2024 | COT - RSBU - Interior Shear Bracing | Passed | Passed shear wall inspection 9//10/2024 | |
| 10/03/2024 | RSBU - Building Progress | Passed | 10/3/24: reinforcement at entry way ok to proceed | |
| 11/06/2024 | COT - BULD - SWG Clearance | Passed | 11-6-24, approved for Southwest Gas connection. | |
| 11/06/2024 | COT - RSEL - Electrical Final | Passed | 11-6-24, electrical final approved pending installation of gas meter. | |
| 11/06/2024 | COT - RSEL - Outdoor Lighting | Passed | 11-6-24, outdoor lighting final approved. | |
| 11/06/2024 | COT - RSME - Mechanical Final | Passed | 11-6-24, mechanical final approved. | |
| 11/06/2024 | COT - RSPL - Plumbing Final | Passed | 11-6-24, plumbing final approved pending installation of gas meter. | |
| 11/06/2024 | ENGR Engineering Final | Passed | Remove nursery stakes | |
| 11/14/2024 | RSBU - Building Final | Passed | 11-14-24, building final approved. |