Permit: TC-MDP-0424-00372
Permit Details
Apply Date:
04/04/2024
Applicant:
Daria Hopkins
Description:
SFR MERI132021 T21-M0062
Permit Reviews
Permit Number - TC-MDP-0424-00372
Permit Status: Inspections
Permit Description: SFR MERI132021 T21-M0062
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/10/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/10/2024 | APPROVED |
04/04/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 04/09/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0424-00372
Permit Status: Inspections
Permit Description: SFR MERI132021 T21-M0062
Total Outstanding Activity Conditions - 6
Date | Name |
---|---|
04/01/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
04/05/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
04/05/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
04/05/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
04/05/2024 | Post-Tension Inspection Report is required. |
04/05/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Conditions
Permit Number - TC-MDP-0424-00372
Permit Status: Inspections
Permit Description: SFR MERI132021 T21-M0062
Date | Description | Comments |
---|---|---|
04/01/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/05/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-MDP-0424-00372
Permit Description: SFR MERI132021 T21-M0062
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/05/2024 | COT - RSPL - Rough Soil | Passed | 11-5-24, underground plumbing verified as per approved plans. Okay to backfill with shading. | |
11/05/2024 | COT - RSPL - Sewer | Passed | 11-5-24, sewer connection verified as per approved plans. Okay to backfill with shading. | |
11/05/2024 | COT - RSPL - Yard Water Line | Passed | 11-5-24, main water line connection verified as per approved plans. Okay to backfill with shading. | |
11/05/2024 | COT - RSPL - Backwater Valve | Passed | 11-5-24, backwater valve verified as per approved plans. Okay to backfill with shading. | |
11/13/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 11-13-24, excavation/rebar/zoning verified as per approved plans. Okay to pour concrete. | |
11/13/2024 | COT - RSBU - Preslab | Passed | 11-13-24, preslab verified as per approved plans. Okay to pour concrete. | |
11/13/2024 | COT - RSEL - Electrical Underground | Passed | 11-13-24, electrical underground verified as per approved plans. Okay to pour concrete. | |
11/13/2024 | COT - RSEL - Grounding/Bonding | Passed | 11-13-24, grounding /bonding as per approved plans. Okay to pour concrete. |