Permit: TC-MDP-0423-00898
Permit Details
Apply Date:
06/10/2024
Applicant:
Celina Rodriguez
Description:
SFR BT2685-228 T22-M0012
Permit Reviews
Permit Number - TC-MDP-0423-00898
Permit Status: Issued
Permit Description: SFR BT2685-228 T22-M0012
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/10/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 06/10/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0423-00898
Permit Status: Issued
Permit Description: SFR BT2685-228 T22-M0012
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
06/10/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
06/10/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
06/10/2024 | Post-Tension Inspection Report is required. |
06/10/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
06/10/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0423-00898
Permit Status: Issued
Permit Description: SFR BT2685-228 T22-M0012
Date | Description | Comments |
---|---|---|
06/10/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
04/13/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-MDP-0423-00898
Permite Description: SFR BT2685-228 T22-M0012
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/05/2024 | COT - RSBU - Preslab | N/A | Re-inspection required | 7/5/24: missing post tension |
07/05/2024 | COT - RSEL - Grounding/Bonding | N/A | Re-inspection required | 7/5/24: missing post tension |
10/17/2024 | COT - RSPL - Sewer | N/A | Re-inspection required | 10-17-24, possible leak at hcs connection. |
10/30/2024 | BULD - Electrical Clearance | N/A | Re-inspection required | 10-30-24, gfci cover missing. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-MDP-0423-00898
Permit Description: SFR BT2685-228 T22-M0012
Total Completed Inspections - 13
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/26/2024 | COT - RSPL - Yard Water Line | Passed | Main water line is ran from meter box to house in trench with blue tracer wire wrapped around pex line. Water line is holding 70 # air pressure for test purposes because meters are not available yet. Okay to shade pipe and backfill trench. | |
06/26/2024 | COT - RSPL - Rough Soil | Passed | Plumbing underground is complete to 5' outside building. No County approval to connect underground plumbing to main sewer line. Okay to proceed with shading pipes under slab and backfilling for compaction preparing for slab on grade. | |
07/09/2024 | COT - RSBU - Preslab | Passed | ||
07/09/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
07/09/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
07/09/2024 | COT - RSEL - Electrical Underground | Passed | ||
07/29/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | Exterior and interior walls are properly secured to concrete floor with shot pins, j-bolts, titan bolts, or masa clips. Plywood sheathing is installed and secured to studs per plan requirements for shear walls. Shear wall hold downs are installed with the required nails in plate and bolted through bottom plate with a titan bolts. Okay to proceed with mechanical, electrical, and plumbing rough-in. | |
07/29/2024 | COT - RSBU - Roof Nailing | Passed | Roof trusses are properly installed per truss calc's and nailed to the top plate and H2.5 clips are properly installed and nailed to top plate. Okay to proceed with rough-in of mechanical, electrical, and plumbing. | |
09/25/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Mechanical, electrical, and plumbing rough-in is complete. Okay to proceed with installation of insulation and drywall. | |
09/25/2024 | COT - RSPL - Gas Pressure Test | Passed | Gas line is holding 15 psi of air. Okay to proceed with other work. | |
10/18/2024 | COT - RSPL - Sewer | Passed | 10/18/24: Leak at HCS has been fixed. | |
10/18/2024 | COT - RSBU - Interior Shear Bracing | Passed | Interior sheet rock is properly secured to studs per plan requirements for an interior shear wall. Okay to proceed with tape, texture, hand painting. | |
11/01/2024 | BULD - Electrical Clearance | Passed | 11-1-24, electrical panel cleared to be be energized. |