Permit: TC-MDP-0423-00888
Permit Details
Apply Date:
02/01/2024
Applicant:
Daria Hopkins
Description:
SFR MER1502580 T21-M0076 REV1 roof covering change
Permit Reviews
Permit Number - TC-MDP-0423-00888
Permit Status: Complete
Permit Description: SFR MER1502580 T21-M0076 REV1 roof covering change
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/19/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/22/2024 | APPROVED |
02/01/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 02/07/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0423-00888
Permit Status: Complete
Permit Description: SFR MER1502580 T21-M0076 REV1 roof covering change
Date | Description | Comments |
---|---|---|
02/01/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
02/01/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
02/01/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
02/07/2024 | Post-Tension Inspection Report is required. | |
04/12/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
07/22/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
02/07/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0423-00888
Permit Description: SFR MER1502580 T21-M0076 REV1 roof covering change
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/22/2024 | COT - RSPL - Yard Water Line | Passed | Water line is connected to the main water meter and is under street pressure. Blue tracer wire is installed from meter to house. Okay to shade pipe and backfill trench. | |
05/22/2024 | COT - RSPL - Sewer | Passed | Underground plumbing and sewer line are connected and under a 10' water test with no leaks. Okay to shade pipes and backfill trenches. | |
05/22/2024 | COT - RSPL - Rough Soil | Passed | Underground plumbing and sewer line are connected and under a 10' water test with no leaks. Okay to shade pipes and backfill trenches. | |
06/07/2024 | COT - RSBU - Preslab | Passed | ||
06/07/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
06/07/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
06/07/2024 | COT - RSEL - Electrical Underground | Passed | ||
06/21/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
06/21/2024 | COT - RSBU - Roof Nailing | Passed | ||
07/19/2024 | BULD - Electrical Clearance | Passed | ||
07/19/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
07/19/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
08/01/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
09/20/2024 | COT - BULD - SWG Clearance | Passed | SWG for meter only | |
10/03/2024 | COT - RSEL - Electrical Final | Passed | ||
10/03/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
10/03/2024 | COT - RSME - Mechanical Final | Passed | ||
10/03/2024 | COT - RSPL - Plumbing Final | Passed | ||
10/03/2024 | ENGR Engineering Final | Passed | ||
10/03/2024 | RSBU - Building Final | Passed | ||
10/03/2024 | RSBU - Building Progress | Passed |