Permit: TC-MDP-0423-00875
Permit Details
Apply Date:
05/10/2023
Applicant:
Daria Hopkins
Description:
SFR MER1402190 T21-M0078
Permit Reviews
Permit Number - TC-MDP-0423-00875
Permit Status: Complete
Permit Description: SFR MER1402190 T21-M0078
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/08/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/12/2024 | APPROVED |
05/12/2023 | ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 | 05/16/2023 | APPROVED |
Conditions
Permit Number - TC-MDP-0423-00875
Permit Status: Complete
Permit Description: SFR MER1402190 T21-M0078
Date | Description | Comments |
---|---|---|
05/15/2023 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. | |
05/12/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
05/12/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
08/09/2024 | Post-Tension Inspection Report is required. | |
04/12/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
08/09/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
05/12/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
05/15/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0423-00875
Permit Description: SFR MER1402190 T21-M0078
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/02/2023 | COT - RSPL - Rough Soil | Passed | ||
08/02/2023 | COT - RSPL - Yard Water Line | Passed | ||
08/08/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
08/08/2023 | COT - RSBU - Preslab | Passed | ||
08/08/2023 | COT - RSEL - Electrical Underground | Passed | ||
08/08/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
08/30/2023 | COT - RSBU - Roof Nailing | Passed | ||
09/14/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
10/25/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
10/25/2023 | BULD - Electrical Clearance | Passed | 10/25/23: TEP ECO clearance issued 1/25/24 clerance resent |
|
10/25/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
11/20/2023 | COT - RSBU - Interior Shear Bracing | Passed | ||
11/21/2023 | COT - RSPL - Sewer | Passed | ||
02/12/2024 | COT - BULD - SWG Clearance | Passed | ||
02/21/2024 | RSBU - Building Final | Passed | ||
02/21/2024 | ENGR Engineering Final | Passed | trees in backyard no properly staked, check irrigation in backyard observed 3-4 inches of watery mud, sewer cleanouts not set to grade, open excavation at irrigation box, front yard. |
|
02/21/2024 | RSBU - Building Progress | Passed | trees in backyard no properly staked, check irrigation in backyard, observed 3-4 inches of watery mud, sewer cleanouts not set to grade, open excavation at irrigation box, front yard. |
|
02/21/2024 | COT - RSPL - Plumbing Final | Passed | ||
02/21/2024 | COT - RSME - Mechanical Final | Passed | ||
02/21/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
02/21/2024 | COT - RSEL - Electrical Final | Passed |