Permit: TC-MDP-0423-00868
Permit Details
Apply Date:
05/03/2023
Applicant:
Mark Alteri
Description:
SFR CVPLAN3 T22-M0044
Permit Reviews
Permit Number - TC-MDP-0423-00868
Permit Status: Complete
Permit Description: SFR CVPLAN3 T22-M0044
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/04/2023 | ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 | 05/05/2023 | APPROVED |
09/21/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/21/2023 | APPROVED |
Conditions
Permit Number - TC-MDP-0423-00868
Permit Status: Complete
Permit Description: SFR CVPLAN3 T22-M0044
Date | Description | Comments |
---|---|---|
05/05/2023 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. | |
05/04/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
09/21/2023 | Post-Tension Inspection Report is required. | |
05/04/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
05/05/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0423-00868
Permit Description: SFR CVPLAN3 T22-M0044
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/31/2023 | COT - RSPL - Backwater Valve | Passed | ||
05/31/2023 | COT - RSPL - Rough Soil | Passed | ||
05/31/2023 | COT - RSPL - Sewer | Passed | Approved connected to main, okay to backfill | |
05/31/2023 | COT - RSPL - Yard Water Line | Passed | Approved, okay to shade cover progress areas | |
06/05/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
06/05/2023 | COT - RSBU - Preslab | Passed | ||
06/05/2023 | COT - RSEL - Electrical Underground | Passed | ||
06/05/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
07/17/2023 | COT - RSBU - Roof Nailing | Passed | ||
07/17/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
08/23/2023 | BULD - Electrical Clearance | Passed | TEP ECO | |
09/15/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
09/21/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
10/16/2023 | COT - RSBU - Interior Shear Bracing | Passed | Interior shear walls in garage and 2nd floor are properly screwed off 7" apart. Okay to tape and texture walls. | |
12/11/2023 | COT - BULD - SWG Clearance | Passed | SWG clearance issued | |
12/11/2023 | COT - RSEL - Electrical Final | Passed | ||
12/11/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
12/11/2023 | COT - RSME - Mechanical Final | Passed | ||
12/11/2023 | COT - RSPL - Plumbing Final | Passed | ||
12/11/2023 | RSBU - Building Final | Passed | ||
12/11/2023 | RSBU - Building Progress | Passed | ||
12/12/2023 | ENGR Engineering Final | Passed | 1) no address posted FYI, Exterior of homes must be move in ready |