Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
05/02/2023
Applicant:
Mark Alteri
Description:
SFR CVPLAN3 T22-M0044

Permit Reviews

Permit Number - TC-MDP-0423-00863
Permit Status: Complete
Permit Description: SFR CVPLAN3 T22-M0044
Start Date Submittal Complete Date Status  
05/04/2023 ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 05/05/2023 APPROVED Review Details
10/06/2023 ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 10/09/2023 APPROVED Review Details
10/09/2023 RESTAMP - RESIDENTIAL v.1 10/09/2023 APPROVED Review Details
09/21/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/21/2023 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0423-00863
Permit Status: Complete
Permit Description: SFR CVPLAN3 T22-M0044
Date Description Comments
05/05/2023 Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents.
05/04/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
09/21/2023 Post-Tension Inspection Report is required.
05/04/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
05/05/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-MDP-0423-00863
Permite Description: SFR CVPLAN3 T22-M0044
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
08/31/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Re-inspection required Not ready. Add 16 gauge metal straps to the top plate and 3" vent line. Add blocking underneath tub, register chase and laundry room. Add fire foam to top penetrations that are not being utilized. Receptacle in master bedroom needs to be moved over to follow 6' 12' rule. Secure EV line. Fully pressurize pex lines. Add smoke detector near bedrooms per plan. 8/31/2023
11/27/2023 COT - RSBU - Masonry Pregrout N/A Not Applicable
11/28/2023 COT - RSEL - Electrical Final N/A Re-inspection required 11/28/23: no ladder to check AC disconnect, sinks don't have p traps installed, toilet missing at downstairs bathroom, condensation line exterior needs coupling pointing down installed
11/28/2023 COT - RSME - Mechanical Final N/A Re-inspection required 11/28/23: no ladder to check AC disconnect, sinks don't have p traps installed, toilet missing at downstairs bathroom, condensation line exterior needs coupling pointing down installed
11/28/2023 COT - RSPL - Plumbing Final N/A Re-inspection required 11/28/23: no ladder to check AC disconnect, sinks don't have p traps installed, toilet missing at downstairs bathroom, condensation line exterior needs coupling pointing down installed
11/28/2023 RSBU - Building Final N/A Re-inspection required 11/28/23: no ladder to check AC disconnect, sinks don't have p traps installed, toilet missing at downstairs bathroom, condensation line exterior needs coupling pointing down installed

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0423-00863
Permit Description: SFR CVPLAN3 T22-M0044
Total Completed Inspections - 23
Date Description Inspector Results Comments
05/30/2023 COT - RSPL - Rough Soil Passed
05/30/2023 COT - RSPL - Sewer Passed
05/30/2023 COT - RSPL - Yard Water Line Passed
05/30/2023 COT - RSPL - Backwater Valve Passed
06/02/2023 COT - RSBU - Preslab Passed
06/02/2023 COT - RSEL - Electrical Underground Passed
06/02/2023 COT - RSEL - Grounding/Bonding Passed
06/02/2023 COT - RSBU - Excavation/Rebar/Zoning Passed
07/10/2023 COT - RSBU - Exterior Clips/Sheathing Passed
07/10/2023 COT - RSBU - Roof Nailing Passed
08/07/2023 BULD - Electrical Clearance Passed TEP ECO
08/31/2023 COT - RSPL - Gas Pressure Test Passed
09/07/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Approved. Corrections were made. 9/7/2023
09/26/2023 COT - RSBU - Interior Shear Bracing Passed
09/26/2023 COT - RSBU - Firewall/Fire Barrier/Firestop Passed
11/28/2023 RSBU - Building Progress Passed
11/28/2023 COT - RSEL - Outdoor Lighting Passed
11/28/2023 COT - BULD - SWG Clearance Passed
11/30/2023 COT - RSEL - Electrical Final Passed 11/30/23: all corrections made
11/30/2023 COT - RSME - Mechanical Final Passed 11/30/23: all corrections made
11/30/2023 COT - RSPL - Plumbing Final Passed 11/30/23: all corrections made
11/30/2023 RSBU - Building Final Passed 11/30/23: all corrections made
12/01/2023 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CBT LOT 8 RECORDED NBE_V1.PDF DOCUMENTS VIEW
PT REPORT LOT 8-2023-09-20_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CBT 8 PP FOR PERMIT_V1.PDF DOCUMENTS VIEW
CBT 8 PT CERT-2023-05-02_V1.PDF DOCUMENTS VIEW