Permit Details

Status:
Complete
Type:
Model Building Permit
Apply Date:
09/08/2023
Applicant:
Stephanie Bebee
Description:
SFR CVPLAN2.5 T22-M0062

Permit Reviews

Permit Number - TC-MDP-0423-00861
Permit Status: Complete
Permit Description: SFR CVPLAN2.5 T22-M0062
Start Date Submittal Complete Date Status  
11/17/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/17/2023 APPROVED Review Details
09/08/2023 ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 09/15/2023 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0423-00861
Permit Status: Complete
Permit Description: SFR CVPLAN2.5 T22-M0062
Date Description Comments
09/08/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
09/11/2023 Post-Tension Inspection Report is required.
09/08/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0423-00861
Permit Description: SFR CVPLAN2.5 T22-M0062
Total Completed Inspections - 22
Date Description Inspector Results Comments
10/03/2023 COT - RSPL - Sewer Passed
10/03/2023 COT - RSPL - Rough Soil Passed 10/3/23: plumbing per plan ok to backfill. Shading is required
10/03/2023 COT - RSPL - Backwater Valve Passed
10/03/2023 COT - RSPL - Yard Water Line Passed
10/12/2023 COT - RSEL - Grounding/Bonding Passed
10/12/2023 COT - RSEL - Electrical Underground Passed
10/12/2023 COT - RSBU - Preslab Passed
10/12/2023 COT - RSBU - Excavation/Rebar/Zoning Passed
11/13/2023 COT - RSBU - Exterior Clips/Sheathing Passed Exterior shear wall sheathing is properly nailed off, anchor bolts are installed in load bearing walls with proper plate washers. Okay to proceed with rough-in of other trades and stucco installation.
11/13/2023 COT - RSBU - Roof Nailing Passed Roof sheathing is properly nailed off, H2.5 clips are attached to all exterior wall rafters, TJI joists hangers are properly attached to ledger board and nailed off. Okay to proceed with drying in of roof.
12/11/2023 BULD - Electrical Clearance Passed TEP ECO
01/16/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
01/16/2024 COT - RSPL - Gas Pressure Test Passed
02/09/2024 COT - RSBU - Interior Shear Bracing Passed 2/9/24: Interior shear walls are properly installed and screwed off per plans. Okay to proceed with tape and texture.
04/10/2024 COT - BULD - SWG Clearance Passed SWG for meter only
04/30/2024 COT - RSEL - Electrical Final Passed
04/30/2024 COT - RSEL - Outdoor Lighting Passed
04/30/2024 COT - RSME - Mechanical Final Passed
04/30/2024 RSBU - Building Progress Passed
05/01/2024 COT - RSPL - Plumbing Final Passed 5/1/24: PVC pipes coming through roof have been painted to protect them from the sun. All other work is complete and operational. Okay to issue Certificate of Occupancy when Fire & Engineering sign off on permit.
05/01/2024 RSBU - Building Final Passed 5/1/24: PVC pipes coming through roof have been painted to protect them from the sun. All other work is complete and operational. Okay to issue Certificate of Occupancy when Fire & Engineering sign off on permit.
05/01/2024 ENGR Engineering Final Passed All looks good

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
PT REPORT LOT 50-2023-11-17_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CBT 50 PP FOR PERMIT_V1.PDF DOCUMENTS VIEW
CBT 50 PT CERT-2023-09-08_V1.PDF DOCUMENTS VIEW