Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-MDP-0423-00858
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
10058 S ARNOLD RANCH CT
Address NEW:
10058 S ARNOLD RANCH CT
Apply Date:
08/14/2023
Applicant:
Amy Stokes, Operations Accountant
Description:
SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2 Structural calcs and Post grade,
Permit Reviews
Permit Number - TC-MDP-0423-00858
Permit Status: Inspections complete
Permit Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2
Structural calcs and Post grade,
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/15/2023 | ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 | 08/17/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0423-00858
Permit Status: Inspections complete
Permit Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2
Structural calcs and Post grade,
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 08/15/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 08/15/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 08/15/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 08/15/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 08/16/2023 | Post-Tension Inspection Report is required. |
| 08/16/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0423-00858
Permit Status: Inspections complete
Permit Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2
Structural calcs and Post grade,
| Date | Description | Comments |
|---|---|---|
| 08/15/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0423-00858
Permite Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2
Structural calcs and Post grade,
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/08/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | N/A | Re-inspection required | Missing anchor bolts at garage shear wall, anchor bolts at shear walls and perimeter of house loose throughout. Tighten all anchor bolts, add shot pins to sole plates where marked, missing rsp4 clip back right side of house, missing truss calcs. |
| 05/13/2024 | BULD - Electrical Clearance | N/A | Re-inspection required | Missing breakers in panel and temporary electrical outlet is not installed on panel box. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0423-00858
Permit Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2
Structural calcs and Post grade,
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/05/2024 | COT - RSPL - Sewer | Passed | ||
| 03/05/2024 | COT - RSPL - Rough Soil | Passed | ||
| 03/05/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 03/20/2024 | COT - RSBU - Preslab | Passed | ||
| 03/20/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 03/20/2024 | COT - RSEL - Electrical Underground | Passed | ||
| 03/20/2024 | COT - RSPL - Backwater Valve | Passed | ||
| 03/20/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 04/08/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 04/10/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 05/13/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Interior mechanical, electrical, and plumbing rough-in is complete. Okay to proceed with insulation and drywall installation. | |
| 05/15/2024 | BULD - Electrical Clearance | Passed | TEP eco | |
| 05/31/2024 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 07/24/2024 | RSBU - Building Final | Passed | Construction, mechanical, electrical, and plumbing work is complete. Mechanical, electrical, and plumbing fixtures are installed and functional. Electrical panel is properly labeled and AFCI & GFCI breakers are installed. A/C unit has the correct size breaker installed. Okay to issue Certificate of Occupancy after all other departments inspections are completed. | |
| 07/24/2024 | RSBU - Building Progress | Passed | Construction, mechanical, electrical, and plumbing work is complete. Mechanical, electrical, and plumbing fixtures are installed and functional. Electrical panel is properly labeled and AFCI & GFCI breakers are installed. A/C unit has the correct size breaker installed. Okay to issue Certificate of Occupancy after all other departments inspections are completed. | |
| 07/24/2024 | COT - RSME - Mechanical Final | Passed | Construction, mechanical, electrical, and plumbing work is complete. Mechanical, electrical, and plumbing fixtures are installed and functional. Electrical panel is properly labeled and AFCI & GFCI breakers are installed. A/C unit has the correct size breaker installed. Okay to issue Certificate of Occupancy after all other departments inspections are completed. | |
| 07/24/2024 | COT - BULD - SWG Clearance | Passed | Gas valves are installed on all locations for gas appliances. Okay to install meter and turn on gas. SWG Clearance issued to Southwest Gas Company. | |
| 07/24/2024 | COT - RSEL - Electrical Final | Passed | Construction, mechanical, electrical, and plumbing work is complete. Mechanical, electrical, and plumbing fixtures are installed and functional. Electrical panel is properly labeled and AFCI & GFCI breakers are installed. A/C unit has the correct size breaker installed. Okay to issue Certificate of Occupancy after all other departments inspections are completed. | |
| 07/24/2024 | COT - RSEL - Outdoor Lighting | Passed | Outdoor lighting is properly installed and operational per plan and city guidelines. | |
| 07/24/2024 | COT - RSPL - Plumbing Final | Passed | Construction, mechanical, electrical, and plumbing work is complete. Mechanical, electrical, and plumbing fixtures are installed and functional. Electrical panel is properly labeled and AFCI & GFCI breakers are installed. A/C unit has the correct size breaker installed. Okay to issue Certificate of Occupancy after all other departments inspections are completed. | |
| 07/24/2024 | COT - RSPL - Gas Pressure Test | Passed | Gas line is under air pressure test and holding 12 pounds of air with no leaks. Okay to proceed. | |
| 07/30/2024 | ENGR Engineering Final | Passed | Tie tree correctly to left of driveway, remove nursery stake on the one to the right. Cut down the clean outs please. |