Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
08/14/2023
Applicant:
Amy Stokes, Operations Accountant
Description:
SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2 Structural calcs and Post grade,

Permit Reviews

Permit Number - TC-MDP-0423-00858
Permit Status: Inspections complete
Permit Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2 Structural calcs and Post grade,
Start Date Submittal Complete Date Status  
08/15/2023 ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 08/17/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0423-00858
Permit Status: Inspections complete
Permit Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2 Structural calcs and Post grade,
Total Outstanding Activity Conditions - 6
Date Name
08/15/2023 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
08/15/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
08/15/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
08/15/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
08/16/2023 Post-Tension Inspection Report is required.
08/16/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-0423-00858
Permit Status: Inspections complete
Permit Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2 Structural calcs and Post grade,
Date Description Comments
08/15/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0423-00858
Permite Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2 Structural calcs and Post grade,
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
04/08/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Re-inspection required Missing anchor bolts at garage shear wall, anchor bolts at shear walls and perimeter of house loose throughout. Tighten all anchor bolts, add shot pins to sole plates where marked, missing rsp4 clip back right side of house, missing truss calcs.
05/13/2024 BULD - Electrical Clearance N/A Re-inspection required Missing breakers in panel and temporary electrical outlet is not installed on panel box.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0423-00858
Permit Description: SFR RKK35I T21-M0091, Revision-1 frame walk redlines, Revision-2 Structural calcs and Post grade,
Total Completed Inspections - 22
Date Description Inspector Results Comments
03/05/2024 COT - RSPL - Sewer Passed
03/05/2024 COT - RSPL - Rough Soil Passed
03/05/2024 COT - RSPL - Yard Water Line Passed
03/20/2024 COT - RSBU - Preslab Passed
03/20/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
03/20/2024 COT - RSEL - Electrical Underground Passed
03/20/2024 COT - RSPL - Backwater Valve Passed
03/20/2024 COT - RSEL - Grounding/Bonding Passed
04/08/2024 COT - RSBU - Roof Nailing Passed
04/10/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
05/13/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Interior mechanical, electrical, and plumbing rough-in is complete. Okay to proceed with insulation and drywall installation.
05/15/2024 BULD - Electrical Clearance Passed TEP eco
05/31/2024 COT - RSBU - Interior Shear Bracing Passed
07/24/2024 RSBU - Building Final Passed Construction, mechanical, electrical, and plumbing work is complete. Mechanical, electrical, and plumbing fixtures are installed and functional. Electrical panel is properly labeled and AFCI & GFCI breakers are installed. A/C unit has the correct size breaker installed. Okay to issue Certificate of Occupancy after all other departments inspections are completed.
07/24/2024 RSBU - Building Progress Passed Construction, mechanical, electrical, and plumbing work is complete. Mechanical, electrical, and plumbing fixtures are installed and functional. Electrical panel is properly labeled and AFCI & GFCI breakers are installed. A/C unit has the correct size breaker installed. Okay to issue Certificate of Occupancy after all other departments inspections are completed.
07/24/2024 COT - RSME - Mechanical Final Passed Construction, mechanical, electrical, and plumbing work is complete. Mechanical, electrical, and plumbing fixtures are installed and functional. Electrical panel is properly labeled and AFCI & GFCI breakers are installed. A/C unit has the correct size breaker installed. Okay to issue Certificate of Occupancy after all other departments inspections are completed.
07/24/2024 COT - BULD - SWG Clearance Passed Gas valves are installed on all locations for gas appliances. Okay to install meter and turn on gas. SWG Clearance issued to Southwest Gas Company.
07/24/2024 COT - RSEL - Electrical Final Passed Construction, mechanical, electrical, and plumbing work is complete. Mechanical, electrical, and plumbing fixtures are installed and functional. Electrical panel is properly labeled and AFCI & GFCI breakers are installed. A/C unit has the correct size breaker installed. Okay to issue Certificate of Occupancy after all other departments inspections are completed.
07/24/2024 COT - RSEL - Outdoor Lighting Passed Outdoor lighting is properly installed and operational per plan and city guidelines.
07/24/2024 COT - RSPL - Plumbing Final Passed Construction, mechanical, electrical, and plumbing work is complete. Mechanical, electrical, and plumbing fixtures are installed and functional. Electrical panel is properly labeled and AFCI & GFCI breakers are installed. A/C unit has the correct size breaker installed. Okay to issue Certificate of Occupancy after all other departments inspections are completed.
07/24/2024 COT - RSPL - Gas Pressure Test Passed Gas line is under air pressure test and holding 12 pounds of air with no leaks. Okay to proceed.
07/30/2024 ENGR Engineering Final Passed Tie tree correctly to left of driveway, remove nursery stake on the one to the right. Cut down the clean outs please.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
1_APPLICATION_V1.PDF DOCUMENTS VIEW
1_SITEPLAN_V1.PDF DOCUMENTS VIEW
1_SPECIAL INSPECTION CERT-2023-08-14_V1.PDF DOCUMENTS VIEW