Apply Date:
04/03/2023
Applicant:
Mark Alteri
Description:
SFR CVPLAN2.5 T22-M0062
Permit Reviews
Permit Number - TC-MDP-0423-00833
Permit Status: Complete
Permit Description: SFR CVPLAN2.5 T22-M0062
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/16/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/22/2023 | APPROVED |
04/07/2023 | ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 | 04/12/2023 | APPROVED |
10/06/2023 | ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 | 10/09/2023 | APPROVED |
Conditions
Permit Number - TC-MDP-0423-00833
Permit Status: Complete
Permit Description: SFR CVPLAN2.5 T22-M0062
Date | Description | Comments |
---|---|---|
04/11/2023 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. | |
04/07/2023 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
04/07/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/11/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-MDP-0423-00833
Permite Description: SFR CVPLAN2.5 T22-M0062
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/16/2023 | COT - RSBU - Interior Shear Bracing | N/A | Re-inspection required | 8-16-23: North exterior wall is not constructed per listing. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-MDP-0423-00833
Permit Description: SFR CVPLAN2.5 T22-M0062
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/28/2023 | COT - RSPL - Yard Water Line | Passed | ||
04/28/2023 | COT - RSPL - Sewer | Passed | ||
04/28/2023 | COT - RSPL - Rough Soil | Passed | ||
05/03/2023 | COT - RSEL - Grounding/Bonding | Passed | Ufer ground is in place. | |
05/18/2023 | COT - RSBU - Roof Nailing | Passed | ||
05/18/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
06/14/2023 | BULD - Electrical Clearance | Passed | ||
07/12/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
07/12/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
08/23/2023 | COT - RSBU - Interior Shear Bracing | Passed | 8/8/23: cancel per Mark. 8-16-23: North exterior wall is not constructed per listing. 8/23/23: all interior sheet rock approved. North walls on 1st & 2nd story's are vertical hung 5/8" type X rock |
|
11/02/2023 | COT - RSPL - Plumbing Final | Passed | ||
11/02/2023 | COT - RSPL - Backwater Valve | Passed | ||
11/02/2023 | COT - RSME - Mechanical Final | Passed | ||
11/02/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
11/02/2023 | COT - RSEL - Electrical Underground | Passed | ||
11/02/2023 | COT - RSBU - Preslab | Passed | ||
11/02/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
11/02/2023 | COT - BULD - SWG Clearance | Passed | 11/2/23: SWG clearance issued | |
11/08/2023 | COT - RSEL - Electrical Final | Passed | 11/8/23: Outlet in kitchen has been moved to within two feet of countertop end. | |
11/08/2023 | RSBU - Building Final | Passed | 11/8/23: Outlet in kitchen has been moved to within two feet of countertop end. Okay to issue Certificate of Occupancy for this address. | |
11/08/2023 | RSBU - Building Progress | Passed | 11/8/23: Outlet in kitchen has been moved to within two feet of countertop end. |