Permit: TC-MDP-0326-00182
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
5955 E BENBURB LN
Address NEW:
5955 E BENBURB LN
Apply Date:
03/17/2026
Applicant:
Candis Benson
Description:
New Residential Model Plan (Model master plan TC-MDP-1224-01415) Rev 2
Permit Reviews
Permit Number - TC-MDP-0326-00182
Permit Status: Inspections complete
Permit Description: New Residential Model Plan (Model master plan TC-MDP-1224-01415) Rev 2
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/24/2026 | SPECIAL INSPECTION REVIEW v.1 | 07/27/2026 | APPROVED |
| 03/19/2026 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 04/02/2026 | APPROVED |
Conditions
Permit Number - TC-MDP-0326-00182
Permit Status: Inspections complete
Permit Description: New Residential Model Plan (Model master plan TC-MDP-1224-01415) Rev 2
| Date | Description | Comments |
|---|---|---|
| 03/20/2026 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 03/20/2026 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 03/17/2026 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 03/17/2026 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 03/17/2026 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ | |
| 03/20/2026 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 03/17/2026 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0326-00182
Permit Description: New Residential Model Plan (Model master plan TC-MDP-1224-01415) Rev 2
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/20/2026 | COT - RSPL - Rough Soil | Passed | 04/20/2026 All fixtures holding under test. Okay to backfill, shading required. |
|
| 04/20/2026 | COT - RSPL - Sewer | Passed | 04/20/2026 Connected to HCS and holding under test. Okay to backfill, shading required. |
|
| 04/20/2026 | COT - RSPL - Yard Water Line | Passed | 04/20/2026 Okay to backfill, shading required. |
|
| 04/27/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 04/27/2026 Approved per plan and reinforcements. Okay for concrete placement. |
|
| 04/27/2026 | COT - RSBU - Preslab | Passed | 04/27/2026 Approved per plan and reinforcements. Okay for concrete placement. |
|
| 04/27/2026 | COT - RSEL - Electrical Underground | Passed | ||
| 04/27/2026 | BULD - Electrical Clearance | Passed | 04/27/2026 Clearance TEP ECO. |
|
| 05/12/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | same day corrections made 5.11.26 Approved |
|
| 05/12/2026 | COT - RSBU - Roof Nailing | Passed | ||
| 05/27/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 5.27.26 Approved |
|
| 05/27/2026 | COT - RSPL - Gas Pressure Test | Passed | 5.27.26 Approved |
|
| 06/11/2026 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 07/20/2026 | COT - BULD - SWG Clearance | Passed | Clearance for Southwest Gas. 7/20/2026 | |
| 07/30/2026 | COT - RSEL - Electrical Final | Passed | ||
| 07/30/2026 | COT - RSEL - Outdoor Lighting | Passed | ||
| 07/30/2026 | COT - RSME - Mechanical Final | Passed | 07/30/2026 Added strap to air duct laying on attic platform 4' o.c. |
|
| 07/30/2026 | COT - RSPL - Plumbing Final | Passed | ||
| 07/30/2026 | ENGR Engineering Final | Passed | ||
| 07/30/2026 | RSBU - Building Final | Passed | 07/30/2026 All conditions satisfied. |
|
| 07/30/2026 | RSBU - Building Progress | Passed |