Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections
Type:
Model Building Permit
Address:
9544 E MEOLA DR
Address NEW:
9544 E MEOLA DR
Apply Date:
07/07/2026
Applicant:
Celina Rodriguez
Description:
Mirador Point 2037-225 (2024 IRC) (Model Master Plan TC-MDP-0226-00090)

Permit Reviews

Permit Number - TC-MDP-0326-00171
Permit Status: Inspections
Permit Description: Mirador Point 2037-225 (2024 IRC) (Model Master Plan TC-MDP-0226-00090)
Start Date Submittal Complete Date Status  
07/13/2026 SITE FROM MODEL PERMIT - SUBDIVISION v.1 07/20/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0326-00171
Permit Status: Inspections
Permit Description: Mirador Point 2037-225 (2024 IRC) (Model Master Plan TC-MDP-0226-00090)
Total Outstanding Activity Conditions - 3
Date Name
03/13/2026 Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections.
03/13/2026 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
07/20/2026 Post-Installed Anchor Inspection Report is required.

Conditions

Permit Number - TC-MDP-0326-00171
Permit Status: Inspections
Permit Description: Mirador Point 2037-225 (2024 IRC) (Model Master Plan TC-MDP-0226-00090)
Date Description Comments
03/13/2026 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
03/13/2026 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-MDP-0326-00171
Permite Description: Mirador Point 2037-225 (2024 IRC) (Model Master Plan TC-MDP-0226-00090)
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
08/26/2026 BULD - Electrical Clearance N/A Canceled 8-26-26 Cancel per super.
09/15/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Re-inspection required 9/15/26: provide a support for 1st floor lavatory dwv, provide kitchen exhausts support, correct leak at upstairs dwv located at west restroom wall, fire foam upstairs chute and chute above door header at entryway of upstairs bedroom-south room, tape Tear to flex at upstairs northeast bedroom, per C404.4 of the IECC, hot pex lines 1" in diameter and smaller must be insulated.

Completed Inspections

Permit Status: Inspections
Permit Number: TC-MDP-0326-00171
Permit Description: Mirador Point 2037-225 (2024 IRC) (Model Master Plan TC-MDP-0226-00090)
Total Completed Inspections - 11
Date Description Inspector Results Comments
07/28/2026 COT - RSPL - Rough Soil Passed 07/28/2026
Holding under test - okay to backfill, shading required.
07/28/2026 COT - RSPL - Sewer Passed 07/28/2026
Holding under test to HCS with green tracer - okay to backfill, shading required.
07/28/2026 COT - RSPL - Yard Water Line Passed 07/28/2026
Holding under test. Okay to backfill. Shading required.
08/03/2026 COT - RSBU - Excavation/Rebar/Zoning Passed
08/03/2026 COT - RSBU - Preslab Passed 08/03/2026
Moved holdowns at least 1" away from form to encase. Ok to pour.
08/03/2026 COT - RSEL - Electrical Underground Passed 08/03/2026
Added UG conduit to kitchen island.
08/24/2026 COT - RSBU - Roof Nailing Passed 8-24-26 items corrected on site OK to proceed
08/24/2026 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 8-24-26 items corrected on site OK to proceed
08/27/2026 BULD - Electrical Clearance Passed 8-27-26 ECO clearance approved
09/16/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 9-16-26 All items have been corrected. OK to insulate.
09/25/2026 COT - RSBU - Interior Shear Bracing Passed 9-25-26 drywall nailing approved. All collection were made during the time of the inspection OK to proceed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
MIRADOR POINT - LOT 129 START_V1.PDF DOCUMENTS VIEW
MP 129 SIC-2026-07-07_V1.PDF DOCUMENTS VIEW