Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/01/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 04/05/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0324-00360
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
03/28/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
04/04/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
04/04/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
04/04/2024 | Post-Tension Inspection Report is required. |
04/04/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-MDP-0324-00360
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Date | Description | Comments |
---|---|---|
03/28/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0324-00360
Permite Description: SFR BT2013-140 T22-M0036
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/27/2024 | RSBU - Building Progress | N/A | Not Applicable | |
09/27/2024 | COT - RSEL - Electrical Final | N/A | Re-inspection required | Laundry receptacle is on lighting circuit. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0324-00360
Permit Description: SFR BT2013-140 T22-M0036
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/18/2024 | COT - RSPL - Yard Water Line | Passed | ||
04/18/2024 | COT - RSPL - Sewer | Passed | ||
04/18/2024 | COT - RSPL - Rough Soil | Passed | ||
05/01/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Concrete forms are set, post tension cabling is properly installed and supported off of ground, rebar reinforcement is installed per plans, underground plumbing is properly wrapped for protection, Ufer ground is installed, and all shear wall & masa clips are installed. Okay to pour concrete. | |
05/01/2024 | COT - RSBU - Preslab | Passed | Concrete forms are set, post tension cabling is properly installed and supported off of ground, rebar reinforcement is installed per plans, underground plumbing is properly wrapped for protection, Ufer ground is installed, and all shear wall & masa clips are installed. Okay to pour concrete. | |
05/01/2024 | COT - RSEL - Electrical Underground | Passed | Concrete forms are set, post tension cabling is properly installed and supported off of ground, rebar reinforcement is installed per plans, underground plumbing is properly wrapped for protection, Ufer ground is installed, and all shear wall & masa clips are installed. Okay to pour concrete. | |
05/01/2024 | COT - RSEL - Grounding/Bonding | Passed | Concrete forms are set, post tension cabling is properly installed and supported off of ground, rebar reinforcement is installed per plans, underground plumbing is properly wrapped for protection, Ufer ground is installed, and all shear wall & masa clips are installed. Okay to pour concrete. | |
05/17/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | Exterior shear walls are properly secured to concrete floor with masa clips, shot pins, or a/b bolts. Straps are secured with nails on large headers, shear wall hold downs are properly secured with nails in every hole, and plywood sheathing for shear walls is properly nailed per plans and code. Okay to proceed. | |
05/17/2024 | COT - RSBU - Roof Nailing | Passed | Roof trusses are properly secured to top plate with H2.5 clips. Plywood sheathing is properly nailed to trusses per plan and code. | |
06/14/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
06/17/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 6/17/24: Mechanical, electrical, and plumbing rough-in is complete. Penetrations and rips in vapor barrier have been caulked. Penetrations through top plates for line set have been fire foamed. Anchor bolts have been installed in shear wall in main bathroom. Okay to proceed with installation of insulation and drywall. | |
07/01/2024 | COT - RSBU - Interior Shear Bracing | Passed | Drywall is properly screwed per plans for the interior shear walls. Okay to proceed with tape, texture, and paint. | |
07/12/2024 | BULD - Electrical Clearance | Passed | Okay to energize. Issuing an ECO Clearance to TEP. | |
08/12/2024 | COT - BULD - SWG Clearance | Passed | Gas valves are installed at water heater, furnace, and kitchen stove. Okay to install meter and turn on gas. SWG Clearance issued to Southwest Gas Company. | |
09/27/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
09/27/2024 | COT - RSME - Mechanical Final | Passed | ||
09/27/2024 | COT - RSPL - Plumbing Final | Passed | ||
09/27/2024 | RSBU - Building Final | Passed | ||
10/02/2024 | COT - RSEL - Electrical Final | Passed | Construction is complete. Okay to issue Certificate of Occupancy. | |
10/02/2024 | ENGR Engineering Final | Passed | CO Ready |