Permit Details

Status:
Inspections Complete
Type:
Model Building Permit
Apply Date:
04/01/2024
Applicant:
Celina Rodriguez
Description:
SFR BT2013-140 T22-M0036

Permit Reviews

Permit Number - TC-MDP-0324-00359
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Start Date Submittal Complete Date Status  
04/01/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 04/05/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-MDP-0324-00359
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Total Outstanding Activity Conditions - 5
Date Name
03/28/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
04/04/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/04/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
04/04/2024 Post-Tension Inspection Report is required.
04/04/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Conditions

Permit Number - TC-MDP-0324-00359
Permit Status: Inspections complete
Permit Description: SFR BT2013-140 T22-M0036
Date Description Comments
03/28/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0324-00359
Permite Description: SFR BT2013-140 T22-M0036
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
09/27/2024 RSBU - Building Progress N/A Not Applicable
09/27/2024 COT - RSEL - Electrical Final N/A Re-inspection required need more clamps on AC seal tight.
09/27/2024 COT - RSME - Mechanical Final N/A Re-inspection required Provide ladder for attic access.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-MDP-0324-00359
Permit Description: SFR BT2013-140 T22-M0036
Total Completed Inspections - 20
Date Description Inspector Results Comments
04/18/2024 COT - RSPL - Rough Soil Passed
04/18/2024 COT - RSPL - Yard Water Line Passed
04/18/2024 COT - RSPL - Sewer Passed
05/01/2024 COT - RSBU - Excavation/Rebar/Zoning Passed Concrete forms are set, post tension cabling is properly installed and supported off of ground, rebar reinforcement is installed per plans, underground plumbing is properly wrapped for protection, Ufer ground is installed, and all shear wall & masa clips are installed. Okay to pour concrete.
05/01/2024 COT - RSBU - Preslab Passed Concrete forms are set, post tension cabling is properly installed and supported off of ground, rebar reinforcement is installed per plans, underground plumbing is properly wrapped for protection, Ufer ground is installed, and all shear wall & masa clips are installed. Okay to pour concrete.
05/01/2024 COT - RSEL - Electrical Underground Passed Concrete forms are set, post tension cabling is properly installed and supported off of ground, rebar reinforcement is installed per plans, underground plumbing is properly wrapped for protection, Ufer ground is installed, and all shear wall & masa clips are installed. Okay to pour concrete.
05/01/2024 COT - RSEL - Grounding/Bonding Passed Concrete forms are set, post tension cabling is properly installed and supported off of ground, rebar reinforcement is installed per plans, underground plumbing is properly wrapped for protection, Ufer ground is installed, and all shear wall & masa clips are installed. Okay to pour concrete.
05/13/2024 COT - RSBU - Exterior Clips/Sheathing Passed Bottom plates are properly secured to concrete floor with masa clips or ab bolts. Plywood sheathing for exterior shear walls is properly nailed per plans and code. Shear wall straps are installed and properly secured with nails to wall framing. Okay to proceed.
05/13/2024 COT - RSBU - Roof Nailing Passed Roof trusses are properly installed and secured to top plate with H2.5 clips. Plywood sheathing is properly nailed to trusses per plan and code. Okay to proceed with plumbing top out.
06/14/2024 COT - RSPL - Gas Pressure Test Passed
06/17/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 6/17/24: Mechanical, electrical, and plumbing rough-in is complete. Penetrations and rips in vapor barrier have been caulked. DWV is full of water with no leaks. Exhaust fan in main bathroom is properly wired and light fixture in hallway is properly secured to trusses. Okay to proceed with installation of insulation and drywall.
07/03/2024 COT - RSBU - Interior Shear Bracing Passed 7/3/24: sheet rock on interior shear walls is properly screwed. Okay to proceed with tape, texture, and paint.
07/12/2024 BULD - Electrical Clearance Passed Okay to energize. Issuing an ECO Clearance to TEP.
08/27/2024 COT - BULD - SWG Clearance Passed SWG for meter only
09/27/2024 COT - RSEL - Outdoor Lighting Passed
09/27/2024 COT - RSPL - Plumbing Final Passed
09/27/2024 ENGR Engineering Final Passed CO ready
09/27/2024 RSBU - Building Final Passed
10/02/2024 COT - RSEL - Electrical Final Passed Construction is complete. Okay to issue Certificate of Occupancy.
10/02/2024 COT - RSME - Mechanical Final Passed Construction is complete. Okay to issue Certificate of Occupancy.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
BELLA TIERRA PHASE 1 - LOT 1 START_V1.PDF DOCUMENTS VIEW
BT 1 SIC-2024-04-01_V1.PDF DOCUMENTS VIEW