Permit: TC-MDP-0324-00307
Permit Details
Apply Date:
03/08/2024
Applicant:
Helen Ormsby
Description:
Blackhawk H30A Model Plan
Permit Reviews
Permit Number - TC-MDP-0324-00307
Permit Status: Issued
Permit Description: Blackhawk H30A Model Plan
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/20/2024 | REQUIRES RESUBMIT |
03/15/2024 | SITE FROM MODEL PERMIT - PRODUCTION v.1 | 03/25/2024 | APPROVED |
12/20/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 12/26/2024 | APPROVED |
Conditions
Permit Number - TC-MDP-0324-00307
Permit Status: Issued
Permit Description: Blackhawk H30A Model Plan
Date | Description | Comments |
---|---|---|
03/15/2024 | Post-Installed Anchor Inspection Report is required. | |
03/08/2024 | Post-Tension Inspection Report is required. | |
03/15/2024 | Post-Tension Inspection Report is required. | |
03/08/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
03/08/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
03/15/2024 | Special Inspection for Soil Testing. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-MDP-0324-00307
Permite Description: Blackhawk H30A Model Plan
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/04/2024 | COT - RSBU - Exterior Clips/Sheathing | N/A | Canceled | Canceled per contractor. 9/4/2024 |
09/04/2024 | COT - RSBU - Roof Nailing | N/A | Canceled | Canceled per contractor. 9/4/2024 |
09/25/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Partial Pass | 9/25/24: blocking in garage on both sides of portal needed. Okay to insulate rest of house. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-MDP-0324-00307
Permit Description: Blackhawk H30A Model Plan
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/09/2024 | COT - RSPL - Backwater Valve | Passed | Okay to backfill. Shading required. 8/9/2024 | |
08/09/2024 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading required. 8/9/2024 | |
08/09/2024 | COT - RSPL - Sewer | Passed | Okay to backfill. Shading required. 8/9/2024 | |
08/09/2024 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading required. 8/9/2024 | |
08/20/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
08/20/2024 | COT - RSBU - Preslab | Passed | ||
08/20/2024 | COT - RSEL - Electrical Underground | Passed | ||
08/20/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
09/05/2024 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
09/05/2024 | COT - RSBU - Roof Nailing | Passed | ||
09/11/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO 9/11/2024 | |
09/25/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
09/26/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | PASSED 9/26/2024 | |
10/11/2024 | COT - RSBU - Interior Shear Bracing | Passed | 10/11/24 PASS | |
11/19/2024 | COT - BULD - SWG Clearance | Passed | 11-19-24, approved for Southwest Gas Co. to install meter. | |
11/29/2024 | COT - RSEL - Electrical Final | Passed | 11-22-24, plumbing, electrical, mechanical, outdoor lighting, and building final all approved. | |
11/25/2024 | COT - RSME - Mechanical Final | Passed | 11-25-24, approved | |
11/26/2024 | COT - RSEL - Outdoor Lighting | Passed | 11-26-24,electrical, mechanical, plumbing, outdoor lighting, and building final approved. | |
11/26/2024 | COT - RSPL - Plumbing Final | Passed | 11-26-24, plumbing final approved | |
11/26/2024 | ENGR Engineering Final | Passed | CO ready | |
11/26/2024 | RSBU - Building Final | Passed | 11-26-24, building final approved | |
11/26/2024 | RSBU - Building Progress | Passed | 11-26-24, building final approved |