Permit: TC-MDP-0324-00293
Permit Details
Status:
Inspections Complete
Type:
Model Building Permit
Address:
7558 S CELINA WY
Address NEW:
7558 S CELINA WY
Apply Date:
03/07/2024
Applicant:
Helen Ormsby
Description:
Blackhawk H30K Model Plan
Permit Reviews
Permit Number - TC-MDP-0324-00293
Permit Status: Inspections complete
Permit Description: Blackhawk H30K Model Plan
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/10/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/12/2024 | APPROVED |
| 03/11/2024 | SITE FROM MODEL PERMIT - SUBDIVISION v.1 | 03/21/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-MDP-0324-00293
Permit Status: Inspections complete
Permit Description: Blackhawk H30K Model Plan
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/07/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Conditions
Permit Number - TC-MDP-0324-00293
Permit Status: Inspections complete
Permit Description: Blackhawk H30K Model Plan
| Date | Description | Comments |
|---|---|---|
| 03/21/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 03/21/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
| 03/07/2024 | Post-Tension Inspection Report is required. | |
| 03/07/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 03/21/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 03/21/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0324-00293
Permite Description: Blackhawk H30K Model Plan
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/03/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Re-inspection required (with fee) | Fresh air must be 10' away from vents. Not ready. 6/3/24: all penetrations going through vapor barrier must be sealed, shear wall at first floor not properly fastened throughout, seal all penetrations going through second floor decking, supports on horizontal DWV runs missing throughout, properly support flex duct throughout, seal mechanical chase at second floor and first floor, smoke detectors missing outside of bedrooms, refrigerant lines must be brazed in, STOPPED INSPECTION MORE ITEMS MAY BE ADDED. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-MDP-0324-00293
Permit Description: Blackhawk H30K Model Plan
Total Completed Inspections - 21