Permit Details

Status:
Issued
Type:
Model Building Permit
Apply Date:
03/29/2024
Applicant:
Daria Hopkins
Description:
SFR MERI156021 T21-M0063

Permit Reviews

Permit Number - TC-MDP-0324-00287
Permit Status: Issued
Permit Description: SFR MERI156021 T21-M0063
Start Date Submittal Complete Date Status  
04/01/2024 SITE FROM MODEL PERMIT - PRODUCTION v.1 04/05/2024 APPROVED Review Details
12/19/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/19/2024 APPROVED Review Details
10/09/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/09/2024 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0324-00287
Permit Status: Issued
Permit Description: SFR MERI156021 T21-M0063
Date Description Comments
04/03/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/03/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/03/2024 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
04/03/2024 Post-Tension Inspection Report is required.
03/05/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
03/05/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.
04/03/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
04/03/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Completed Inspections

Permit Status: Issued
Permit Number: TC-MDP-0324-00287
Permit Description: SFR MERI156021 T21-M0063
Total Completed Inspections - 13
Date Description Inspector Results Comments
10/24/2024 COT - RSPL - Rough Soil Passed 10-24-24, underground plumbing per approved plans. Okay to backfill.
10/24/2024 COT - RSPL - Sewer Passed 10-24-24, sewer connection approved. Okay to backfill.
10/24/2024 COT - RSPL - Yard Water Line Passed 10-24-24, main water line inspection approved. Okay to backfill.
11/01/2024 COT - RSBU - Excavation/Rebar/Zoning Passed 11-1-24, setbacks verified per approved plans.
11/01/2024 COT - RSEL - Electrical Underground Passed 11-1-24, approved-conduit in place.
11/01/2024 COT - RSBU - Preslab Passed 11-1-24, preslab per approved plans. Okay to pour concrete.
11/01/2024 COT - RSEL - Grounding/Bonding Passed 11-1-24, grounding/bonding inspection per approved plans. Okay to pour concrete.
11/15/2024 COT - RSBU - Roof Nailing Passed 11-15-24, roof nailing and truss bracing verified as per approved plans.
11/15/2024 COT - RSBU - Exterior Clips/Sheathing Passed 11-15-24, exterior clips/sheathing ,roof nailing and truss bracing verified as per approved plans.
12/10/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Passed 12/10/24
12/10/2024 BULD - Electrical Clearance Passed Ready for temp power 12/10/24 CLEARANCE ECO
12/10/2024 COT - RSPL - Gas Pressure Test Passed Holds pressure 12/10/24 passed
12/19/2024 COT - RSBU - Interior Shear Bracing Passed 12/19/24 ok to proceed.

Documents

File Name Document Type  
241720 - VALENCIA CROSSING PH2 LOT 95 - PT REPORT-2024-12-12_V1.PDF DOCUMENTS VIEW
LOT 95 REVISED SPECIAL INSPECTION CERTIFICATE-2024-10-08_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
LOT 95 APPLICATION_V1.PDF DOCUMENTS VIEW
LOT 95 PLOT PLAN_V1.PDF DOCUMENTS VIEW
LOT 95 SPECIAL INSPECTION CERTIFICATE-2024-03-29_V1.PDF DOCUMENTS VIEW