Permit Reviews

Permit Number - TC-MDP-0323-00815
Permit Status: Complete
Permit Description: SFR DRHOH35B21 T21-M0045
Start Date Submittal Complete Date Status  
04/05/2023 ZZZMODEL PERMIT REVIEW RESIDENTIAL v.1 04/11/2023 APPROVED Review Details
08/03/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/05/2023 APPROVED Review Details

Conditions

Permit Number - TC-MDP-0323-00815
Permit Status: Complete
Permit Description: SFR DRHOH35B21 T21-M0045
Date Description Comments
04/10/2023 Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents.
04/05/2023 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/05/2023 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
04/05/2023 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
04/05/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
04/10/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Completed Inspections

Permit Status: Complete
Permit Number: TC-MDP-0323-00815
Permit Description: SFR DRHOH35B21 T21-M0045
Total Completed Inspections - 20
Date Description Inspector Results Comments
05/05/2023 COT - RSPL - Rough Soil Passed
05/05/2023 COT - RSPL - Sewer Passed
05/05/2023 COT - RSPL - Yard Water Line Passed
05/12/2023 COT - RSBU - Excavation/Rebar/Zoning Passed
05/12/2023 COT - RSBU - Preslab Passed
05/12/2023 COT - RSEL - Electrical Underground Passed
05/12/2023 COT - RSEL - Grounding/Bonding Passed
06/20/2023 COT - RSBU - Exterior Clips/Sheathing Passed Approved. 6/20/2023
06/20/2023 COT - RSBU - Roof Nailing Passed Approved. 6/20/2023
06/29/2023 COT - RSPL - Gas Pressure Test Passed
06/30/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
07/10/2023 BULD - Electrical Clearance Passed Approved, ECO Clearance to TEP is required for construction power
07/10/2023 COT - RSBU - Interior Shear Bracing Passed
08/25/2023 COT - BULD - SWG Clearance Passed Clearance for Southwest Gas. 8/15/2023
08/30/2023 COT - RSEL - Electrical Final Passed
08/30/2023 COT - RSEL - Outdoor Lighting Passed
08/30/2023 COT - RSME - Mechanical Final Passed
08/30/2023 RSBU - Building Final Passed
08/30/2023 COT - RSPL - Plumbing Final Passed
08/30/2023 RSBU - Building Progress Passed

Documents

File Name Document Type  
SVB 46 PT REPORT-2023-08-02_V1.PDF DOCUMENTS VIEW
SVB 46 SIC-2023-08-02_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
SVB 46 SIC-2023-03-30_V1.PDF DOCUMENTS VIEW